2026-11-09 - Regulatory Oversight Committee Meeting
Summary
Built from the posted agenda and the auto-generated caption transcript, which may contain errors; minutes are not yet posted. Public commenters and private residents are not named, and garbled names and figures are omitted.
- Committee members Spellerberg, Oppenheimer and Pankonin asked questions; the captions garble several surnames and the chair is not identifiable, so attendance is not listed. Minutes of an earlier committee meeting were approved by voice vote (mover and seconder per the captions: Spellerberg and Oppenheimer; ambiguous).
- Theme of the evening: level-setting on the current regulatory environment for data centers, and listening, before any ordinance options are considered. No vote on any regulation.
- Public Works Director Cotter walked through a two-page fact sheet (Data Center Regulatory Oversight): the state definition of a data center (peak demand of 10 megawatts or more), state requirements on electric cost reimbursement and water-supply notice and review, state Public Utilities Commission siting of transmission lines over 115 kV, and city rules (light and heavy industrial zoning, light trespass, 75 decibel industrial noise limit with a 95 decibel impulsive limit, 25 foot front setbacks plus buffers beside residential, 45 and 55 foot habitable height limits, water, wastewater and industrial pretreatment review, and the private utility right-of-way permit).
- Planning staff said light complaints are checked with a meter at the property line, and that the applicant, then the property owner, is responsible for enforcement. Staff were asked to return with the industrial pretreatment questionnaire, examples of what the noise levels sound like, a clarification of state versus city roles for groundwater, a review of the Wyoming wastewater incident, and whether any private project has ever required a performance bond (staff knew of none; public projects use performance and payment bonds).
- City Attorney Pfeifle gave a national overview: number of data centers operating and planned, state moratorium and ban attempts, peer-city actions (a one-year moratorium in Madison, Wisconsin; a six-month moratorium extended in Aberdeen; overlay districts in Vermillion), the state statute that does not preempt local regulation, legal limits on zoning power (regulatory takings, no regulating a lawful use out of existence), and regulatory models from Morton County (North Dakota), Maricopa County (Arizona) and Pennsylvania guidance covering power, water, noise (including low-frequency measurement), decommissioning bonds and e-waste. He asked the committee to share proposals with his office for legal review and said code enforcement relies mostly on voluntary compliance, with injunctions as the strongest court remedy.
- Committee schedule: a Nebraska site visit that week; the November 30 meeting will have four presentations (electric power usage, water usage, the Public Utilities Commission process, environmental standards); written public input is requested by November 27 and will be entered into the record on November 30.
- Developer presentation (Sioux Falls Technology Park Data Center Site): the developer, Gemini, owns land at East Rice Street and Veterans Parkway, said it has no signed end user, and described city conditions (domestic water only, closed-loop cooling, setbacks and berms, paying for utility grid upgrades), a preliminary tax estimate for a 500 megawatt campus, and a schedule of earliest energization late 2028 with most power late 2029. It asked for regulatory certainty for projects already approved. A civil engineer working on data centers said no US state or national rule covers anything beyond A-weighted noise, and that cooling fans are the main source of low-frequency noise. The developer has no operating data center to point to.
- Open committee discussion: requests to look at surety or bonding, what requirements can run with the land to a later owner, deeper study of the Morton County, Maricopa County and Pennsylvania examples, requiring the utility agreement before a building permit is issued, and noise monitoring and enforcement.
- Public input (about two dozen speakers, not named): supporters were local engineering firms, the chamber of commerce, construction employers and trade unions citing jobs, apprenticeships and tax revenue, and asking for clear rules; opponents and neighbors, including residents just outside city limits, asked for a one- or two-year moratorium (Hyperscale Data Center Moratorium) and raised low-frequency noise, water supply and cooling-chemical disposal, light, traffic, health, decommissioning, diesel backup generators, possible loss of state tax revenue, grandfathering of existing approvals, and a good-neighbor development agreement as an alternative. The meeting adjourned after public input.
Data Center Regulatory Oversight
- Staff fact sheet, City Attorney national survey, committee follow-up requests and the November 30 schedule.
Sioux Falls Technology Park Data Center Site
- Developer presentation and committee questions on timeline, noise and benefits; next milestone is the utility's transmission permit application to the state commission.
Hyperscale Data Center Moratorium
- Public comments for and against a moratorium; no committee action.
Agenda
Video
Transcript
YouTube auto-generated captions, lightly redacted for privacy (public commenters and private individuals are not named); speakers are not labelled and names and figures may be garbled.
Transcript
Good afternoon everybody and welcome to
the Sioux Falls Regulatory Oversight
Committee meeting on Monday, November
9th, 2026. I'll note that we have of
members present. Ask one of the
committee members if they'd be willing
to make a motion to approve the minutes
of March 26, 2024.
>> Move approval.
>> Spellerberg.
>> Second, Oppenheimer.
>> Been moved and seconded. All in favor of
voice vote, say aye.
>> Aye.
>> Opposition, same sign. Those minutes are
approved.
Uh this evening our committee meeting uh
is broken down into some various topics
and then opportunity for public input uh
covering a variety of different things
that you want the committee to consider.
Our theme this evening is really in the
area of level setting, understanding
what the current regulation environment
is, and also listening and learning and
so what the concerns are as we enter
into a phase of looking at various
ordinance options and regulatory
opportunities in front of us. So we're
going to go ahead and get started this
evening. I want to welcome forward to
get us started uh the director of public
works, Mark Cotter.
>> Uh good evening, council chair and
council members. I'm Mark Cotter with
the public works team.
Um it was requested to put together a
fact sheet.
Um
and we have question we have additional
copies over by the
door and essentially we laid out the
fact sheet of what are the salient
points today of
of what is um provided with the recent
legislation legislate
what the recent legislature passed at
the state law
um
what the key components of the PUC are
and then what's the current ordinances
of the city of Sioux Falls. And so uh
with your permission, it's two pages. Um
I'll walk you through those key points
and and if we do run out, I know um
Thea will make additional copies.
All right. Um starting off with South
Dakota's codified law,
they first defined data center as a
central repository of electronic data
for information with peak demand of 10
megawatts
or greater.
Next section of the
legislation states that
a provider of electricity shall
establish and maintain separate terms
and conditions for electric service
applicable to a data center
requiring reimbursement for all costs
fairly attributed to the data center
for service
demand and utility consumption including
costs incurred to serve the data center
departs the system or materially reduces
its load.
The next section of that legislation
is requirements prior to commencing
operations in South Dakota.
The data center shall provide notice of
projected water consumption to the to
each local water provider in the area in
which the data center is proposed to be
located.
Each water provider receiving notice
shall provide written determination
whether the data center's projected
water consumption is compatible with the
local water supply.
The operator shall present a copy of
each notice and determination to the
Board of Water Management at the state.
Upon receipt of the water provider's
written determination
SD BWM's
acronym in
the handout
must issue to the operator and general
public a written statement that the
operator has satisfied the requirements
of this section.
Regardless of this
Board of Water Management's issuance of
written statement, the data center must
may not consume an amount
the local water supply exceeding limits
established by order of the board after
allocation to residential and essential
public services.
In establishing allocation limits under
this section, the board shall seek to
ensure water availability and prevent a
disproportionate use of water by data
centers.
So those are the key points in the
state statute. The the state statute is
at 49-50.
Uh, next section is South Dakota Public
Utilities Commission.
So South Dakota PUC, as it's uh acronym,
does not permit data centers. However,
transmission line siting is regulated by
the South Dakota PUC.
The permit trigger,
a new line design for more than 115 kV,
including associated facilities,
generally requires PUC approval before
construction.
An exception applies only if the line is
less than 2,640 ft in length,
crosses no public highway, and uses no
eminent domain for right of way. And the
South Dakota
codified law section is noted there in
the
fact sheet.
Next is general PUC process timeline.
Applicants are encouraged to file at
least 6 months before planned
construction and must notify landowners
within 1
1/2 mi within 30 days after filing.
The PUC schedules a public meeting
within 30 days. Formal formal party
applications are generally due within 60
days unless the order otherwise ordered.
The typical transmission decision
deadline is 12 months after the initial
application,
extendable at the applicant's request.
And there's a PUC siting guide that's
also noted on the fact sheet that's has
more helpful information.
All right, now for about a page and a
half of existing Sioux Falls ordinances
that are in place.
First with zoning. Data centers are
currently allowed in I-1, which is light
industrial,
and I-2 heavy industrial districts.
Lighting.
All building and parking lot lighting is
regulated by Ordinance 160
.491 of the shape places zoning
ordinance.
This section regulates the height of
fixtures as well as the light trespass
maximum at the property line.
Noise.
Industrial normal noise maximum are 75
decibels at all times
with impulsive sound limits set at one
peak of 95 decibels or less
per hour. And then the ordinance is
cited.
Noise is measured by the city at the
nearest edge of the closest adjacent
property line.
Setbacks.
Setbacks are regulated by the Shape
Places zoning ordinance chapter 160.
Generally industrial uses are required a
25-ft front yard setback and further
additional buffer yard setbacks are
required if adjacent to residential.
The zoning ordinance allows conditions
increasing setbacks to be placed on any
rezoning approval.
All right.
Those of you that are following along,
it's on the
uh back sheet of the fact sheet.
Electric rates just in uh general data
centers shall reimburse any provider of
electricity for all costs
fairly attributed to the service demand
and the utility consumption. And the
South Dakota
codified law 49-50-2
is noted. Investor-owned public
utilities are regulated by the South
Dakota PUC.
Uh that state statute is uh noted. And
then we've also if um if by chance one
was located in the city's uh power
territory that um our rates are found at
that uh ordinance in chapter 51.
Height restrictions.
Maximum height for property zoned light
industrial I-1
if it's habitable is 45 ft.
And property zoned heavy industrial I-2
habitable is 55 ft.
For uninhabitable structures under I-1
and I-2 there is no maximum height
requirement and those ordinances noted
are 160.346
and 160.354.
Uh domestic water. The city reviews the
projects requested water demand to
determine whether sufficient system
capacity is available and establishes
the amount of potable water that can be
provided to the proposed development and
what it may be used for. Proposed
developments must comply with the
engineering design standards chapter 10
water mains and all other applicable
ordinances.
Wastewater. Wastewater is regulated by
ordinance
in chapter 53 publicly owned treatment
works.
The proposed development must comply
with the engineering design standards
chapter nine sanitary sewers and all
other applicable ordinances.
Proposed development standard reviews
shall be completed by the city including
the review of existing system capacity
and anticipated wastewater constituents.
Review may include a developer
completing a hydraulic flow study to
ensure sufficient capacity is available
in industrial pre-treatment
questionnaire.
Industrial wastewater. The city
maintains local authority over
wastewater discharge from industrial
facilities to the city's sanitary
system.
This authority is granted through the US
protection
US Environmental Protection Agency the
EPA an industrial pre-treatment program
IPP
administered through the South Dakota
Department of Agriculture and Natural
Resources with local authority granted
to the city to regulate industrial
discharges and to ensure compliance with
local state and federal requirements.
This program establishes the cities
to monitor manage and when necessary
restrict discharges that could
negatively impact the wastewater
collection system treatment processes
public health or the environment.
Next is city of Sioux Falls private
utility permitting process pursuant to
ordinance 96.235
right-of-way and construction
right-of-way construction and
administration. Applicant would be
required to register with the City of
Sioux Falls the right-of-way contractor
meeting and bonding the
meeting the bonding and insurance
requirements.
Once registered
the applicant applies for a private
utility permit which requires a
description of the work to be completed,
what is to be installed and the location
of installation and include a map of the
installation route.
The city reviews the application
including the following, current city
infrastructure and location proposed,
any existing easements in the proposed
location
and potential future development or
right-of-way projects in the proposed
location.
Applicant shall comply with the
conditions of the utility permit and
also comply with the state and federal
laws including but not limited to the
South Dakota PUC and and DANR.
I've noted and put a disclaimer on the
bottom of this information that you can
read and we can also advance this to the
committee
and this fact sheet was prepared for the
City of Sioux Falls Regulatory Oversight
Committee that's updated in November of
2026.
Do you have any questions? I'd be happy
to entertain them.
>> Thank you, Director. Committee members,
questions for Director Cotter on what
he's laid out here of existing
ordinances and so forth.
Councilor Pinkelman.
>> Yes, thank you, Mr. Chair.
I was curious on the industrial
pretreatment questionnaire. I was
wondering what questions are on the
industrial pretreatment questionnaire
that apply to the discharge and disposal
of cooling fluids.
>> I
in in
I'm not an expert on the industrial
pretreatment questionnaire
but essentially that goes through a a
list of questions for any industrial
waste
um and and allows us to
um really start to engage that
uh applicant on
on
anything that they document that goes on
there. So for the next meeting I can
certainly bring what that industrial
pre-treatment questionnaire is and we
can go through that in greater detail.
>> Thank you.
>> Councilor Spellenberg.
>> Thank you Mr. Chair.
Mark thanks for the detail here. You've
done a ton of work on this and we
appreciate it. Um so we're using
interesting terms light trespass. That
means how bright is it going to be if
I'm a neighbor, correct?
>> Yes.
>> So what does the city currently do?
Um I know we have quite a few large
projects out there. How do we do that?
>> Um since that's in the zoning piece I'm
going to bring up Jason Bieber if that's
okay with you and um have him speak to
that piece. Thank you.
>> you.
Uh good evening council. Jason Bieber
representing Planning and Development
Services. Uh great question council
member. We currently have as Mark
indicated a light trespass ordinance.
Uh we
regulate the height of the outdoor
fixtures and then also the amount of
candle lights at the property line.
Uh the ordinance allows a maximum of
what we call three-foot candle lights at
the property line. So we have a meter.
Um I get probably six to 10 complaints a
year then I would go out obviously when
it's dark out, walk the property line
with the meter and make sure that it's
under that three-foot candle light.
>> Please.
>> What happens if it's not? What do we
>> Uh then we would work with the property
owner. It'd obviously be a violation.
Typically most of the the one I just had
worked on it was an apartment complex. I
simply called the property owner and
said hey you have a couple of wall
lights here that are a little bright.
Can you put some shields on them? Um
they obviously complied and put the
shields on and then we make sure that it
does meet the ordinance.
Obviously if it was a property owner
that wasn't so easy to work with we
would go down the uh process of
citations and then obviously going
through the code enforcement through
court and all that stuff.
>> Please continue.
>> Okay, second question 95 decibels for
sound.
How loud is that? Can you give us an
example right now?
>> I wouldn't be able to do that cuz that's
a health
health
department requirement, but we could
probably get you something for that at
the next meeting of what those decibels
sound like. They have a pretty good list
of kind of
what what those would be as part of it.
>> Got it. I think it would be helpful just
to understand how loud it is.
Thank you.
>> Councilor Oppenheimer.
>> Thank you, Mr. Chair.
Couple of questions.
One is
Sorry, I'm looking at multiple
One is a more general question. When
we're talking about the applicant, would
that be I'm going to use Gemini as an
example, but obviously this is we're
looking at moving forward with anyone
anyone particular. Would that be
the end user as the applicant or is that
the group that is preparing
everything? As in would that be Gemini
or would that be who is
who is purchasing the data center?
>> From a planning perspective, going
through the process of the rezonings and
future land use annexations,
we would have the applicant would be
whoever is getting the property ready to
go. That could be the end user. In this
case, it was Gemini. We obviously needed
the property owners
sign off on the application as well.
Those
are those next steps as we talked a
little bit about would be whoever
applies for the building permit
and then builds the facility. That's who
then from lighting aspect, we would come
back on it whoever the property owner
is.
>> And that's the same with water
consumption and
the various other
>> Yep, whoever the current owner is is
kind of who we have the
right to go through the enforcement
process on.
>> Thank you. And I did didn't say at the
beginning, thank you for putting this
together and giving us this information.
I know know, a lot of work.
The next question I had regarding height
restrictions is a is a data center, is
that habitable or uninhabitable?
>> Uh great question. So typically what we
do with height restrictions is as Mark
had indicated is 45 ft in light
industrial, 55 ft in heavy industrial
for uh habitable and structures. So we
would coordinate with our building
permit team.
Um they would look at this and and
classify from a building code
perspective if it's habitable or
uninhabitable. Typically most industrial
uses are uninhabitable. Most people
don't live in there, but we would go
through the building code definition of
habitable.
>> Okay.
So it wouldn't have a height restriction
in this case as it would more like more
than likely be uninhabitable. Is that
correct?
>> Typically that's the case, yes. However,
we do still have to look at other things
like airport fly zones and things like
that. So there could be some other
restrictions that aren't in the zoning
ordinance.
>> Okay.
And
I believe those were all the questions I
had. Thank you. You asked about the
decibels already. That was my next
question. How loud is 95 decibels?
But we had that question, so I'm good.
Thank you.
>> We can get that information, so.
>> Thank you, Councilor.
Councilor Pinkerton, back to you.
>> Thank you, Mr. Chair. This one may take
a a few weeks to answer as well, but um
I was looking at that second the South
Dakota codified law and so I'm not sure
if somebody from the city can answer it
or not, but I'm curious if the city has
a role in carrying out that um South
Dakota codified law 4950-2,
the one that states that
the the provider of electricity shall
establish and maintain separate terms
and conditions for electrical service
and and even gets into including costs
incurred to serve if the data center
departs the system.
So
>> Can I turn to the Director Cotter or the
City Attorney on that?
>> Um I would expect that that would be an
agreement that's
between the
um end user and the electric company.
That's the way I read that, Councilor.
>> Other questions, Councilors?
>> Director Kotter, I've just got a couple
couple questions.
Underneath SDCL 49-54 talking about
water, is the Board of Water Management
an executive branch appointed group or
is that a
that's not an elected body, is it?
>> I need to confirm on that if it's
appointed or if it's elected. I believe
it's appointed, but I'll I'll double
check.
>> Kind of embarrassing, but if it's
elected, I never recall voting for any
of them.
>> Exactly.
I will double check.
>> Just clarifying, we understand your
role, director of public works,
wastewater treatment, the responsibility
of the city over wastewater treatment
from my perspective is pretty clear at
the end of the day. That's your
responsibility, your team's
responsibility. I think we've got a long
track record of that. But walk us
through outside of the wastewater, we've
got groundwater.
So something happens that not just
impacts the wastewater, but impacts the
groundwater. What falls under your
jurisdiction of groundwater impact
versus the South Dakota Department of
Natural Resources, their oversight of
that area? Can Is there a clear divide
of who's responsible something gets into
the groundwater versus the wastewater?
>> I I do think it's very specific for
wastewater and
and just
as it'll start with the industrial
pre-treatment questionnaire,
we do have very specific experts that
work with the industries in town and so
we'll come back and and speak to that.
When you
try to separate the two, whether it is
wastewater or groundwater, these are,
you know, all modern buildings have to
basically be designed so they prevent
that
that happening with any
anything with groundwater. And but that
would fall into the state's role and we
would be certainly there to assist.
Can't think of anything offhand that um
would cause that. And so um but I, you
know, if if a building today is built to
today's building standards
internal collection system, I don't see
um
I don't see how that would actually
um deviate from any other building
that's built. But um we can certainly do
some more research on that as well.
>> I appreciate that, director. And just
following up on that and with Councilor
Panken, and I think between now and the
next one as well, I think a lot of us
have received
phone calls, emails, articles on the
situation in Gillette, Wyoming. And
there's legal activity that's taking
place there, a fine that's been issued
there. I think it'd be helpful for
someone from our team just to kind of
level set on what happened there of what
if that was a construction issue, if
that was a clean out issue, if just so
we're at least talking about the same
things, not opinion on what was right or
wrong, but just level setting on what
took place in Gillette. I think it would
be really helpful as it's used as an
example a lot of what's happening.
>> We'll personally reach out to them and
talk to their uh city officials so we
can come back and
and share with what we've learned.
>> Thank you. And then my final question
would be for either you or Jason. Have
Has there been any project in the city
of Sioux Falls history that's required a
performance bond?
>> Not Not that I am aware of, Jason. Um
when when we hire contractors to do
public improvements in the public's
right of way um and or build a um a um a
public building, that's very common
practice for us inside right of way. But
that's those are performance and payment
bonds, not necessarily on the on the
private side.
>> Thank you. Any final Councilor
Stellerburg.
>> One more question, Mark. When we're
talking about water, I think it's just
helpful if you kind of go through again
what we decided we would allow in this
kind of a project. Can you
reaffirm what we have?
>> I'm sorry. Would you restate
>> question?
>> Yeah. So I think it's important just to
kind of cover what we are allowing. So I
think the pipe size to the location,
wastewater,
just hit those highlights again.
>> Uh certainly. So
when when this applicant initially came
in,
this area was zoned in what we call tier
three. We worked with them
to move it to tier one. We had made it
clear that this was in our master plan.
We had already laid out the water mains
and the sanitary sewer collection mains,
but the fact that
it was in a
it required a change to the future land
use that we said we would support this
provided that they would extend the
public utilities at no reimbursement.
And that means the wastewater collection
system and the water system. And so
they've they've retained local
engineering
support to make those designs that are
very familiar with our standards. And so
that was the first thing.
And then as it comes to water, we've I
think there's been a lot of discussion
about water and we know the value of
water. And so we said from the very
beginning we didn't want water to be
used drinking water to be used for
cooling.
And so that's when we started to talk to
them just about their domestic uses.
And and fortunately
from what we see and read and also have
heard from Gemini in this case is that
they intend to work with an end user
that uses a closed loop
system technology that essentially
you know doesn't rely on
you know a
much water at all except for their
domestic use. And so that would be very
common in any
light industrial
and or commercial application.
And so we've said that from the very
beginning.
We know that from talking with other end
users is very little wastewater that
comes from these facilities.
And so having first said you need to
advance the public utilities, future
public utilities with no reimbursement.
Um, they've agreed to do that and
they've designed those and and their
some of their initial site plans have
laid out those respective easements and
and pipe routings and there's a
wastewater pump station that's required
here.
And then just the very good discussion
on the use of water in the facility. So
does that answer your question?
>> Yeah, mostly. I think just hearing out
loud that I think from our standpoint
we've said it that they only get the
same amount of water as a single family
house or a a small industrial use
facility, correct? To run their
bathrooms, their sinks,
things like that. Yep, thank you.
>> Yeah, you're welcome. Thank you.
>> Thank you, Director.
At this time I'll invite forward the
city attorney, David Pfeifley. The
committee has asked the city attorney to
prepare for us an overview of what's
taking place across the country. We
Director Cotter level set for us on what
some of the existing ordinances
regulations are in our state and our
community. They've asked the attorney to
lay out for us what's taking place
across the country. Good afternoon,
attorney.
>> Thank you, counselor.
City Council, on behalf of the city
attorney's office, I'm David Pfeifley
here to talk with you this evening
about just an overview of data center
regulation that we are seeing across the
country.
You will note that the first slide is
dated and there that is on purpose. This
changes by the day. It's the most fluid
topic I've seen in some time in my 32
career, 32 year career.
Data center, as Director Cotter had told
you, it's defined under state law.
I think this is kind of where the
discussion for us begins. Data center
demand is growing.
A review of national sources is showing
that there are almost 1,400 data centers
already operating in the United States
of various sizes.
And as of October 2nd, they believe
there's going to be about 2,800 more
data centers are planned.
And you can see the megawatt additional
capacities.
AI ready data center capacity is
expected to grow by 33% annually from 25
to 2030
driving a surge in local data center
proposals. I think what you need to
think about with that 33% is
as counselor Spellerberg knows in his in
his industry you're compounding. That's
not a 33% over that time. I took it to
mean 33% each year is growing.
Now
the last one is kind of where
the conversation has moved from
the coasts into the south and the
Midwest where of those 2800 proposed
data centers 39% of them are planned in
the south and in the Midwest.
So looking at the National Conference of
State Legislatures I kept looking at
their site in terms of what's going on
in all the legislatures across the
country.
Over this recent history 16 state
legislatures have recently attempted
moratoriums on data centers
and or bans on data centers.
A moratorium was passed by the state of
New York. I believe that was a one year
moratorium.
Six measures had failed. One was vetoed
I believe by the governor of Maine
while the rest of those proposals are
still in various levels of progress.
As we all know and have discussed in
this last legislative session the state
of South Dakota's legislature adopted
the data center Bill of Rights
but note that that data center Bill of
Rights did not adopt a proposed plan ban
excuse me that was also introduced or a
proposed moratorium.
I also looked this weekend at the city's
16 peer cities.
Of those cities only Lincoln Nebraska so
far has adopted in their city ordinances
a definition for data center.
Madison Wisconsin has adopted a one year
moratorium
that took effect on January 23 of 2026
so that one year moratorium will soon
expire.
The governing body for the city of Fort
Wayne Indiana considered a moratorium
this year, but they did not approve it.
So that is kind of what is going on both
uh on the state side as well as our 16
peer cities.
Now, uh this is a statute uh that is
ga- garnering a lot of attention.
It is specifically saying that the state
will not preempt or otherwise limit the
authority of the governing body of
either a county or municipality.
And it uses the words limiting,
prohibiting, or otherwise regulating.
And some people are taking the statute
to mean that it uh allows free reign of
a county or a municipal government to do
whatever they will with data center
regulation. And I can tell you that that
is
not necessarily the case. Um and I'll
explain in a moment.
Now, under uh
the police powers that you enjoy as an
elected uh local governing body, you
have the power to protect the public
health, safety, and general welfare.
And certainly one of the main mechanisms
that you do that is through your zoning
ordinances, through your zoning power.
As all of you know, that's almost one
half of any
of all the items on your agenda on any
given council meeting. And you make an
incredible amount of influence on how
land use is governed within our city.
So in this case,
uh
you have to look at whether
a uh
any zoning regulation is subject to
change. And the Tillo case, which
happened to come out of Sioux Falls, it
was where
uh the Hy-Vee grocery store is now on
39th and Minnesota Avenue.
Uh at that point it was a proposed
Kmart. Uh at in that instance that
parcel I believe was zoned residential.
Uh the residential properties around it
tried to claim that well we have a
vested interest in that
adjoining parcel remaining residential
rather than commercial. Our state
Supreme Court came back and said you
don't have a vested interest in any
particular zoning classification.
Now zoning authority, even though you
have the power to change a zoning
classification, it doesn't exist in a
vacuum.
Uh your zoning authority is not
unlimited.
Uh probably the most famous case in
South Dakota is SDDS Incorporated versus
the State of South Dakota.
This happened about 25 you know actually
it's 32 years ago it went through the
state legislature.
It was a municipal solid waste facility
proposed for out near Edge Mont in Fall
River County.
Uh the state's board of Minerals and
Environment initially granted them a
five-year
permit for operating that facility.
Uh there was uh
an an initiative enacted thereafter
where the voters said they wanted the
state legislature to actually vote on
whether to approve that permit.
I was working for the State House of
Representatives when this bill came up
and I saw the debate and saw
the the emotions and concerns that were
generated by that bill and it's
remindful of what's going on with data
centers. But the point is the
legislature ultimately approved that
permit.
After that the citizens then did a
referendum
where they where the they undid they
they undone what the legislature had
done. So the permit was revoked.
So what happened was the State Supreme
Court through a series of cases held
that once a permit had been issued that
the landowner had a protected property
interest in using that property so you
couldn't
withdraw or remand that permit.
And here's the the real takeaway of that
case. While property may be regulated to
a certain extent if regulation goes too
far pardon pardon my typo there it will
be recognized as an
impermissible regulatory taking. The
problem of course is to know what is too
far in any given case.
That is where the legal principle of how
far can you regulate any specific type
of business.
You can't
You can place reasonable restrictions on
them through the zoning ordinances and
regulations, but you can't regulate them
out of business.
A real easy example to understand is uh
adult-oriented businesses in terms of
you'll note they are severely restricted
in terms of where they can operate, but
it is not outright banned anywhere
within the state of South Dakota.
There's been quite a bit of litigation
on that.
So in terms of Excuse me. In terms of
how the courts review it, they review it
on a case-by-case basis. So as this
regulatory committee is going through
the process of thinking about proposals,
what would you like to do in terms of a
regulatory response to uh data centers
possibly being in the city of Sioux
Falls?
Uh we would ask that you that you share
your proposals with us first and and our
office can assist you in terms of Is
this something that would comply with
all the legal
uh principles that we've talked about in
terms of Is it going too far or not? As
you can imagine, that is a gray area. It
is not easy to answer and it'll it'll
take a a
good in-depth analysis of your
particular uh proposal.
So uh you had tasked me with uh
explaining what's going on around the
country in terms of regulation, what's
going on.
Uh these
five regulatory focus points are
certainly not my own. They're based on a
toolkit uh provided
in October by the University of
Minnesota, both the Hubert Humphrey
School of Government and their law
school did a joint uh data center
toolkit
that also is based on the National
Association of Counties where they have
uh advising their membership, which is
all the counties across our
What are some considerations for you?
And I want to thank publicly [name redacted], who's a legal intern in our
office. [name redacted] watched hundreds of
hours
of regulatory hearings on data centers
from across the country.
We frankly would have been We just
appreciate his invaluable help with all
this effort. And certainly these focus
points match the hundreds of hours that
he's spent reviewing proposed
regulations across the country.
I think even more importantly
is these five regulatory focus points
match
a national Gallup poll that was done in
May of this year.
And that was entitled reasons Americans
oppose data centers in their local area
by the Gallup foundation. It was dated
May 13th of 2026.
In terms of the opponent side, here's
the main reasons.
Reasons Americans oppose data centers
affect on water and energy resources.
Number two was quality of life concerns
like water and energy resource impacts.
Number three was noise pollution,
air water pollution, light, heat
generated by the facility.
Number four was any economic effects and
number five
reason was negative views of artificial
intelligence.
On the proponent side
the top reasons were again in a national
poll, local economic benefits such as
jobs, tax revenue,
improve the infrastructure of the
community such as new roads, new
business.
Number two was technology benefits for
the community,
AI, inevitable, faster internet service.
Actually number three reason was people
who are already working in the industry
were responding favorably.
And number four other reasons were such
as US competitive
US competitiveness, excuse me, on a
global scale.
Now the local regulatory framework for
zoning, electrical and water have been
discussed by director Cotter already.
I'm going to talk more about kind of
what some other regulatory proposals
we're seeing across the country.
Uh number one, currently the common
zoning categories for data centers from
across the country and again I want to
uh
thank [name redacted] for this. It's by
right approval. If you meet certain
requirements, you are given uh the right
to operate.
Uh
the city's shape places zoning ordinance
back in 2014 was adopted with the
normal or customary conditional use
permit conditions placed right in that
ordinance
and it cut down on the number of uh cup
applications we needed not because the
city was getting slacker on
requirements, but actually placed the
usual and customary conditional use
permit requirements within the ordinance
itself.
Uh number two is approval with a
conditional use permit. You see that
across the country
and number three was certainly special
exceptions.
Some emerging zoning categories are new
types of categories we're seeing through
uh [name redacted] and my research is overlay
districts are being established for data
centers where it can go in a certain
area, but also overlaying that is if you
are a data center, here are some
additional requirements
that are overlaid upon that.
Uh the second one is we're seeing some
communities proposing planned innovation
research technology area. They're trying
to leverage similar type businesses all
in one area, providing that same
infrastructure, being able to have all
of them operate more effectively from a
technology standpoint. And then the
third one is of course we're seeing
specific zoning areas for data centers.
Uh I'm not going to belabor the point on
this one, but it's just showing kind of
the zoning scheme again for the city of
Sioux Falls. It lists on there data
centers falling under the industrial or
I1 light industrial use
as Mark Cotter indicated to you. It's
also under the heavy industrial use.
Those would be allowed as well.
It's where warehouse manufacturing,
that's what the WM stands for. You went
through all these already.
So I'm going to just go through a few
slides in terms of what we're seeing
some other communities doing.
Uh
first one is Morton County, North
Dakota.
A lot of my counterparts in our part of
the world are looking to Morton County.
They have recently enacted quite an
extensive regulatory scheme on data
centers.
And for electrical concerns, they are
stating that the applicant
must show sufficient electrical service
either through onsite generation or
through an agreement with a serving
utility.
And as Mark had already indicated, that
would be an investor owned
utility in all likelihood.
And then the second one that they're
requiring is the utility must certify
electrical capacity has been committed
and that the data center will be built
under cost recovery structures.
Another example that some of you have
mentioned is Maricopa County, Arizona.
In looking at their draft ordinance as
of last week, it has not been adopted
yet to the best of my knowledge. I
didn't check it today. But again, this
topic is so fluid, you never know.
The data center applicant again, written
confirmation from the utility service
providers, availability, capacity.
And then the second one probably mirrors
what our state PUC statute is here.
Terms of the applicant bears the full
cost of any undergrounding any any
adjacent or onsite electrical
infrastructure.
Now
the next one is on noise
concerns, noise measurements.
The Virginia is kind of the state where
where more data centers are probably
located than anywhere in the country and
they're always good to look at in terms
of what what are they doing
regulatorily.
And the city of Chesapeake, Virginia had
has a very informative web page on data
center ordinance and policy.
And they talk about the different types
of decibels and what the sounds are
being measured.
And certainly a counselor Pankonin, I'll
defer to you cuz you've done this as
part of your engineering work, but
here's my lawyer's understanding of what
this page was saying that certainly the
DB decibels type A is a standard for
environmental noise,
but it doesn't always measure any low
frequency sounds that could be generated
at a facility.
DBC
uh is the standard for measuring or
capturing persistent low frequency
drone, whine, or buzz of a large data
center cooling fan. That's directly from
their website.
And then I talked about regulating for a
steady tonal sound as a continuous
unchanging sound and only uh DBC C could
measure that. These are sounds caused by
the data center's cooling systems,
mechanical equipment, electrical noise,
and onsite
backup power equipment.
Again, going back to Morton County on
their noise controls,
uh they require a noise impact study for
any applicant
uh including ambient noise study. Again,
that's ambient is the low frequency or
DBC.
Uh prohibits tonal noise from carrying
beyond the property boundary.
Uh regulates the timing of backup
generator testing to certain hours so
you're not disturbing any nearby
uh properties and then it regulates
noise vibration during
data center operations within set
limits.
Uh there's been some talk certainly and
we've certainly heard the concerns about
what if a data center ceases operations,
what do we do?
Uh the
the University of Minnesota, their
toolkit that just came out
is stating certainly that
decommissioned plans and agreements and
financial requirements are quote
becoming part of the conversation on
local state regulation of data centers.
Uh
and they're noting in their review of
proposed regulation from across the
country, you may require a certain time
frame for cleanup after ceasing
operations. I believe it was 12 months.
And
excuse me, Councilman MacQuarrie, this
is where your question was coming in on
a performance bond, etc.
Uh the University of Minnesota was
certainly noting that
uh local governments are discussing
maybe requiring some type of bond or
letter of credit to cover estimated
costs of decommissioning. So this
certainly would be
a uh a new wrinkle in terms of what's
going on.
But I think what you need to remember in
terms of your authority as a city
council to regulate data centers, they
are a unique use, both in terms of
electrical, in terms of water usage, in
terms of noise generation. All those are
unique elements that require unique
responses and unique regulation. So it's
not singling out data centers simply
because that's who they are. They have
very unique issues attached to the way
they use their property.
The final couple slides I want to point
out is
this Pennsylvania guide is I want to
tell you what the sources were. These
are two counties, Chester and Montgomery
County, but they were using various
models by some unique organizations.
The Pennsylvania Municipal League,
uh
the uh
Pennsylvania Physicians Association,
kind of like our Medical Association
here,
and also PJM Future, which is a leading
environmental
uh group within their state,
came together
and devised these are guides that they
are recommending for local governments
within the state of Pennsylvania.
And it lists eight different
considerations in terms of what uh
potential data center regulations should
address. And I think it does it in a
very succinct way and summarizes up
quite a bit of our research that we've
seen across the country. I'm not going
to read it to you. You can read it for
yourself, but certainly zoning and
placement, power and energy plans, water
usage, wastewater disposal plans.
Uh one that 's not been talked about yet
is the thermal impact mitigation plan as
these places generate heat. How are you
going to
minimize heat impacts?
Excuse me.
And then number five is the noise and
vibration.
This was a suggestion
for these Pennsylvania groups, both
local governments, uh, physicians, and
also an environmental group in terms of
what
types of suggested levels they would
recommend.
Uh, number six was an electronic waste
plan.
Again, similar to the decommissioning
issues in terms of how are we going to
uh, any disposal of server server
infrastructure, hazardous materials,
batteries, electronic waste, etc.
And then also the last one being the
decommissioning plan again. So
terms of those types of things. Finally,
what's going on in South Dakota? Uh,
again, we're seeing Sully County has a
large data center for crypto mining up
uh,
up in their county.
It's generating enough tax revenue where
they are going to fund their schools
100% through that taxation.
They have required environmental impact
reviews on energy demand, water usage,
and possible emissions.
Uh, the city of Vermillion is adding
data centers as an overlay district
with requirements specific uh, for data
centers for noise, water, and cooling
systems. And then finally, the city of
Aberdeen
uh, adopted a six-month uh, moratorium.
They went through a series of uh,
hearings with their city council.
They've just
extended that moratorium another six
months and they're working on
an ordinance right now.
And I want to thank you for your public
service and I always have to put the
caveat at the end. While I'm an
attorney, this is for informational
purposes. I'm not giving you a specific
piece of advice on any specific
proposal. We'll need to see them. So I
appreciate your time and your public
service
and uh open for the questions.
>> Thank you, Attorney Pfeifle. Councilors,
questions?
Councilor Pinkerton.
>> Thank you, Mr. Chair, and thank you,
Attorney Pfeifle.
On the example in Morton County, North
Dakota, um you mentioned that a data
center built under cost recovery
structures, could you just explain that
a little bit more if
um what that might mean in Morton County
with the term cost recovery structures?
>> I wish I could explain that far better,
but it's my understanding that whatever
rates they're paying is paying for
whatever added infrastructure is needed
for that data center, rather than
spreading the cost of that
infrastructure across all the
ratepayers. That's my understanding of
what that would mean.
>> Thanks.
>> Other questions, committee members?
Anything, Councilor Oppenheimer,
anything?
>> Thank you for putting this together.
It's a lot of lot of good information. I
appreciate the examples of what's been
done in
Pennsylvania and in Morton County, and I
think that will be
I think it's going to take us some time
to process this and
uh use it, but thank you so much for
doing this.
>> Thank you.
Uh Attorney Pfeifle, I've got a couple.
First, we're seeing a lot of interplay
here between state and city, and
sometimes there's not the greatest of
communication between different
government bodies.
Um so for example, I mean, I think the
state legislature has made their intent
very clear regarding electric utility
rates. What authority does the city
have? For example, have you seen any
ordinances on a local level that that
require basically the city the state on
two fronts? One is we look at SDCL
49-52.
Before a building permit is issued, the
city needs to see that agreement that's
in place between them and the PUC.
Secondly, uh under the banner what I'm
going to call pay your own way, the city
has adopted uh regarding sales tax that
data centers do not qualify for a sales
tax exemption in Sioux Falls. However,
the sales tax collection power that we
have is vested to us by the state.
The state could take that power away on
January 15th and nullify the work that
we did. Is there an option locally where
we can say if the state does X
it
I'm I'm just trying to think this
through to help us think that through of
how we say this is our principle locally
of pay your own way. And if you can't
pay your own way and the and the rules,
the regulations change that
pulls the permit or something like that.
Am I making sense at all of what I'm
saying?
>> I'd want to unpack that a little more,
Councilor. And certainly on electrical
in particular, I mean, there's such an
overwhelming state presence, regulatory
presence versus the city.
We're very limited in what we really can
do on the electrical side of things. So
certainly we would want to reach out to
the Public Utilities Commission and and
go through some of those scenarios and
see what they would find acceptable
in terms of
various scenarios, this for that type of
situation. We'd be happy to work work
with you on that.
>> Second question I would have is a lot of
times a lot of the concern we're hearing
is the word accountability.
Somebody breaks the rules.
For the [name redacted] family, if I break the
rules and I don't I build within 3 ft of
my shed of the property line, I got to
pay $1,500 bucks. That's not going to go
over well with the [name redacted] household,
the $1,500 thing hitting the pocket.
$1,500 fine for
group X because they go over the
property line,
they're probably going to be like, just
write the check for $1,500 bucks. Is
there an example where the
accountability can be industry specific
or do we get ourselves in trouble where
we've got certain via code violations
for the rest of the community are only a
$500 fine, code violations for this
industry are
$50,000 I'm being exaggerative. But how
do how do we do that with our code
enforcement where a code violation, for
example,
the [name redacted] is very different than the
code violation of another situation.
Walk us through how we make sure there's
appropriate accountability for the size
of organization or entity that we're
talking about.
>> Well, as
you know, as Jason Bieber mentioned on
the citation process, but beyond that,
in terms of code enforcement, the city
goes through a process where we try and
get voluntary compliance with whomever
is violating the code.
And certainly our city team has been
able to get 96% voluntary compliance.
Usually
the moment you tell them, hey, you're
violating the ordinance here, can you
can you remediate? Can you fix it? Get
back on track?
Certainly as you go through the court
process, one possibility is an
injunction, and that's probably our best
and most
heavy hammer that we have where you
can't continue operations if you're
violating
certain types of ordinances. And
certainly based on the type of
violation, we could seek that in the
courts.
And also you'll note that the regulatory
scheme doesn't just involve the city. It
involves
the state. It involves also the federal
EPA, which is granted its
enforcement authority to the the South
Dakota Department of Ag and Natural
Resources. So there's a lot of
regulatory
arsenal behind just the city going after
say one of our ordinance violations, but
there's certainly far more at in our
toolbox.
>> Thank you, sir.
Committee members, any final questions
for the attorney?
All right, seeing none, thank you for
your time this evening.
Committee members wanted to move on to
our next topic of upcoming committee
schedule. Our goal here was to really
quickly just recap for us and for the
community what's coming next. I just
wanted to walk through our next steps as
a committee, see if there's any
clarifying questions that you have or
anything we need to adjust, but go
ahead, Councilor Spellerberg.
>> Thank you, Mr. Chair. I'd like to
actually take this time to
bring up the developer on this project
to maybe have a conversation where
they're at, what what we're looking at
today. I I think they're here today,
correct?
>> Can we hold that just one second till we
get through the committee schedule? And
then we'll get that in open committee
discussions. Is that okay?
So let's just go through the committee
schedule coming up. Coming up, I think
of this Thursday, committee members
along with some other committee members
are going to be taking a trip to tour
some places down in Nebraska to kind of
have a first site visit, not a first
site visit, a firsthand visit of some
different places and listen to some
community members down there. So that's
happening this coming Thursday. Our next
committee meeting is on Monday, November
30th. At that committee meeting, we're
going to have four different
presentations. One on electrical power
usage, understanding that. One on water
usage. One on the PUC process. Just walk
us through. So for example tonight,
Director Cotter laid out for us of when
a PUC permit is needed on a transmission
line. And so that's just one element of
it, but then you have the rates as well.
So we'll have somebody here walking us
through that PUC process. And then
finally, environmental standards of how
that works. So four different
presentations that night for learning.
November 27th is the final deadline that
we're asking community members to submit
things online to us. Community members
are more than welcome to attend on
November 30th and give public input at
that meeting and other future meetings
as well, but for us as we are writing
potential things, we're asking for
November November 27th. All of the
materials that are received by November
27th will be officially put into the
record at the meeting on November 30th.
We're not going to read every element of
it, but it'll be published
electronically. It'll be here physically
in some sort of format. So everything
we've received will be put in the record
that night. So that's what's coming up
over the next month. Committee members,
any questions on our schedule or what
we've got coming up next?
All right. Now we'll move into our next
topic, which is open committee
discussion on what we've heard or what
we're thinking about during our open
committee discussion. Our goals are
really twofold. One is opportunity for
us to ask questions. Our number two is
we want to finish this section with just
giving our staff, the city council
staff, anything specific we've heard
tonight that we want them to further
research, do fact finding on, as we ask
them to go and confirm things, affirm
things, whatever it might, whatever be.
So let's just open it up for open
committee discussion for a few moments.
Councilor Spellerberg, we'll let you get
started.
>> Well, what I just said. How about that?
Would you guys like to come up and have
a conversation about where you're at in
the project?
Thank you.
>> Okay.
Want to introduce yourself and then
Councilor Spellerberg can get us
started.
>> So
good evening, council members. Thank you
for the opportunity to be here tonight.
I'm [name redacted] with Gemini.
And we own the land on the southeast
corner of East Rice Street and Veterans
Parkway
that's
designated for the future Sioux Falls
Technology Park.
Then that sits right across from Excel
substation.
I know our our project has come up in in
various comments and you know, we're
here
to
help clarify some of those questions as
as much as we can.
Some might find it a bit challenging and
to come and speak here tonight, but it
actually pales in comparison
to a parent-teacher conference I have
tomorrow for my twin boys. So
I'm
on on that topic, I just wanted to
clarify something too. I know in some of
the comments I've seen there's been
connections between Google and Gemini.
Gemini has nothing to do with Google.
Actually the the word Gemini means twins
and the name it was named after my boys.
So that's where the name come from. So
we have nothing to do with Google
completely separate from them.
So moving forward, we wanted to discuss,
you know, topics that already have been
brought up, such things as water,
electrics, electricity, noise,
environmental impacts, and other key
points.
Our goal is to provide answers grounded
in facts, which is why we've also
brought with us, you know, a technical
expert that's been working on the
project and has worked with the city
through the
land use amendment, annexation, and even
the zoning process.
We've never suggested the development
shouldn't happen without oversight. In
fact, we spent much of 2025 going
through that
extensive process with the city and we
incorporated and many recommendations
that came out of that.
We believe Sioux Falls can protect its
residents and remain attractive for
substantial and private investment.
Those objectives are not mutually
exclusive.
The area where our property sits,
as mentioned earlier, was already under
consideration for future light
industrial development, although it was,
you know, considered tier three. And
that was prior to our purchase. With the
rail line across the street, Excel
substation and power plant,
as well as numerous transmission lines
crossing the property,
a data center didn't seem so
far-fetched.
In 20 January 2026,
when the city approved the land use
entitlements for our property,
including the zone change,
relying on that approval, Gemini went
ahead and made significant investments
to advance the project with Excel
and other important service providers.
We've also spent considerable dollars
working with South Dakota firms like HR
Green and Infrastructure Design Group
before the construction has even begun.
Some of those groups are here in the
audience today
and may share some comments. We want the
people and the companies already in
Sioux Falls to share in the
opportunities this development can
create. Recently, we've been speaking to
various contractors,
electrical worker unions, other trade
unions, and a lot of that work has been
going to North Dakota, they've shared,
for example, and we want to try and keep
that as much local as possible.
Uh, regarding transparency,
we've always been dedicated to follow
the public process laid out by the city
that all development projects go
through.
Our project was discussed at public
meetings with the planning commission
and city council through every step.
Um,
the future land use amendment,
annexation, and zoning.
We have been discussing the this
opportunity with prospective end users.
That's correct, but do we have any
finalized agreement with an end user
today? No.
There is a big difference between
withholding information and decisions
that simply have not yet been made where
we simply cannot provide that
information.
Our role as the developer is to bring an
experienced operator to this site where
there is a signed agreement we're able
to announce you'll be the first to hear
from us.
Uh, the conditions on this site apply to
whoever builds and runs this campus um,
based on the agreements we are making
and we will make sure that those
commitments are carried through.
Over the past few months, we've spent
considerable hours working with various
consultants to analyze the economic
impact of the project.
We've also reviewed our assumptions with
the Minnehaha County Director of
Equalization's Office and other
stakeholders. From this work, we
prepared a preliminary estimate of what
a fully developed 500 megawatt campus
would generate in tax revenue.
These are scenarios, not guaranteed
revenues, and they depend on what
ultimately gets built.
Uh, we also welcome an independent
review of them. For the city of Sioux
Falls, with respect to just the
electricity taxes, at full operation,
our models show the project would
generate roughly $5 million a year in
municipal electricity taxes for the city
with another $10.6 million in annual
revenue to the state.
This is also additional tax revenue that
would be coming in at a time where
certain
tax potential cuts are being considered.
Our early projections also show that the
project can generate
millions of dollars in property taxes
shared among the city of Minnehaha
and the local school districts.
We'd love the opportunity to work with
the council over the course of the next
few weeks to actually
narrow down on how how much those
dollars will be uh based on what our
consultants are sharing and what
the the county has also provided
information to us. Ultimately,
it's the council's call what to spend
these dollars on, but much of that can
go to for
essential services, schools, parks,
recreation, affordable child care and
housing, and even potentially
lowering the need to raise taxes or the
the burden of taxes for residents.
Uh
one point I know to our neighbors in
Brandon,
from what we've learned from the county,
a big portion of those property taxes
actually would go to the Brandon Valley
School District.
Uh the state aid formula does offset
part of that, so that net benefit needs
to be confirmed with the district and
the state, but that is also a big part
of where taxes go.
The economic potential does not remove
our responsibility. We take
being stewards of this land seriously,
and several safeguards are already
conditions of our approval.
Water is the issue residents have raised
and has come up over in these
conversations just minutes ago.
Our general our January approval already
limits water use strictly to domestic
use, not industrial use. And that is
based on us utilizing a closed loop
cooling system, which will be a crucial
factor and requirement for this project.
So domestic water use being kitchen,
bathrooms, drinking water, and so forth.
We've also incorporated significant
setbacks and berms in our design in
addition to have in addition to having
two major streets on each side of our
project with each Rice East Rice Street
Veterans Parkway as our borders.
With respect to upgrades to the grid, I
know that's come up and definitely
something to further look into with the
PUC, but all along Gemini has been
covering the costs of all these upgrades
so that the cost does not fall on
residents. That is something that has
been
in place with Excel, the main utility
working with us
so that Gemini, although we don't
control the process, we do foot the bill
for the work that Excel will be doing.
We've also voluntarily incorporated the
future expansion of Rice Street into our
design
as part of the development of our site.
We would be potentially offering the
city some of the land we own to widen
East Rice Street for that that future
plan.
There's also another important principle
I just wanted to touch base on which has
come up in some of the conversation
which is just regulatory certainty.
Gemini began this process under the
city's established rules. We engaged
city departments, obtained land use
approvals,
hired local professionals, and invested
in reliance on that process. We then
made significant investments based on
those approvals.
Changing requirements midway through the
development can affect engineering,
financing, infrastructure commitments,
and other negotiations. That is not an
argument against reasonable oversight.
We're prepared to adopt reasonable
standards and work with the city. What
we ask is that the city recognize the
existing approvals and consider
clear communication on those.
What that kind of fairness we believe
matters to every landowner and business
in Sioux Falls that plans ahead.
We follow the process in good faith and
we're here to continue
to earn the community's trust by
answering questions and providing as
much information as possible.
At the same time,
we're not We know that there there
questions that remain. We're not asking
the city to ignore them. We're offering
to help to answer them.
We believe Sioux Falls can protect its
residents, attract future investments,
and establish clear
expectations for every developer that
comes after us. We're committed to
working with the city to make that
happen.
Thank you for your time. We appreciate
the opportunity to continue the
conversation and answer any questions
you may have.
>> Thank you, sir. Councilor Stenberg, I'll
turn it over to you.
>> Thank you for the detail. And from our
standpoint, as you had said, you do not
have an end user.
Correct?
>> Correct.
>> So
time frame wise,
I think the term moratorium has come up
quite often.
What is a realistic time frame from the
day you get an end user until you start
moving dirt to get through the PUC and
everything along with that? Because
obviously we're trying to put good
standards in place here. And it sounds
like you're agreeable to that. But how
much time do we have from the day you
get that contract in place?
>> So
so kind of just to point out two things,
somewhat of two separate paths or
working in in tandem is we are moving
towards submitting a PUC application.
Excel is actually the one that would be
submitting that, not Gemini.
And that is something that
we have covered the cost for. And we've
spent a lot of 2026 working with Excel
on the design of connecting their
substation to our substation. Although
it's just half a mile and we're just
crossing the street, we are going
underground. There is quite a bit of
engineering and a lot of different
reports that need to be put together to
submit an application to the PUC. So
we're going through that process or
preparing for that
right now.
At the same time, we are, you know,
speaking to end users and looking for
that end user during this process as
well.
We would anticipate
right now at the earliest, you know,
even if we do have an end user in place,
let's say
today, for example,
the earliest we would potentially see a
building, a a data center hall
energized, and most of that is
goes through the path of when Excel can
deliver power
would be
late 2028
with the majority of the power most
likely at this point the schedule is for
late 2029.
So between now and then, of course, a
lot of work would be done. For instance,
in 2027
grading could begin and certain work can
start being done. There's also utilities
as
Mr. Cotter has, you know, explained we
need to extend sewer lines, water, and
so forth. So that could also begin in
2027 as well. But our goal is to try and
have that happen in the next
few months. We don't have full control
as far as, you know, securing an end
user and bringing that information to
the city.
But if we could do that in the next few
months and share that with you,
hopefully we'd be able to move forward,
you know, in in 2027 with some of that
initial site work
and moving forward to submitting
a comprehensive complete set of plans
for the city to begin reviewing.
>> Continue. One more.
>> One more question from my standpoint
just would be
you know, obviously once the building is
up, it's too late. So we have to make
sure that we're
getting all these protections in place
for the citizens of Sioux Falls from a
design standpoint cuz that's really what
it's going to come down to is making
sure that we have the design correct
from the sound, light,
water usage.
Realistic time frame on that. What would
you say to that question?
>> As far as
the design of the actual buildings and
when those those would need to be
approved
and we permits would need to be issued
if those were to be submitted
I mean, at the very I mean,
most optimistic, maybe
uh plans could be submitted in in 6 to 9
months, and I mean probably overly
optimistic cuz if you can imagine these
are complicated projects,
uh it would take many months to prepare
plans. Then it would be going to the
city for review, comments, and so forth.
They'd come back with all sorts of
recommendations. A new set of revisions
would have to happen. That in itself
would take many months before actual
uh
plans would be in a position to issue a
permit.
Um so nothing is, you know, imminent at
this time. It It would be,
you know, many months
even after we were to have a end user in
place.
>> Got it. Thank you. That just gives me a
better idea on time frames from this
kind of a project cuz this is obviously
new to us as well.
>> Right.
>> Thank you.
>> All right.
If you're willing, Councilor Councilor
Penkamen.
>> Yeah, thank you. Thank you for being
here, and thank you, Mr. Chair. And And
I just to confirm I think what I was
just hearing is that it's after uh an
end user is in place that that's when
the design gets complete then for that
end user.
>> Correct.
>> And then I have another question that
might be hard to answer if you if you
don't know who the end user is, but
with, you know, I'm not an expert in
um data center and in data center
technology. You know, I I'm a water
engineer by trade, but um not not in any
way the electrical parts and the data
storage and whatnot. That's not where So
but I am interested in this uh
this topic of um
low
frequency and um this, you know, volume
of the the D the C in parentheses that
we just saw on on our attorney's slide.
And I'm curious which part of a data
center creates that if it's like if just
every every chip that's getting cooled
or if it's just the generator or just
kind of which part creates that
that little hum or or that low frequency
noise.
>> Yeah, I I'm not an engineer either. I'm
not I don't want to give you an answer
right off
the cuff without making sure it's
correct. We can get you that
information. I believe that's the one
that's just from the consistent
lower level sound that's that's
happening.
I don't know if maybe you know we have
someone here who is an engineer and
works on data centers maybe she wants to
answer yet if you guys are okay if she
can
>> Please come forward. Yep.
>> She can introduce herself as well.
>> Good evening. Good evening council
members. My name is [name redacted] I'm a civil
engineer with Kimley-Horn.
I've been in the data center space since
2012 working on projects, seeing the
evolution of the industry.
Worked on a lot of different types in in
different parts of the country.
So that's a little bit of background,
but in regards to the
the noise question
it's all very correct what has been
shared today. There's DBA, DBC which
puts a heavier emphasis on the low
frequency noises.
There's also DBG, DBC. They're different
ways to look at the spectrum of noises,
you know, vibrations essentially that
are put out.
It is getting more common. There's not
anything currently in the US that
officially from a state or a national
level that regulates anything but DBA,
which is the most typical. It's what you
can hear to the human ear.
But we are seeing some more local
requests or requirements around DBC or
DBZ.
And it's so what comes from it is some
of the cooling equipment,
some of the the fans in the coolers
um and or chillers.
Um the equipment is very, as you can
imagine, very specific to different
manufacturers and what's selected from
the specifics of the design.
Um but generally to answer your
question, it's the it's the fans from
the coolers.
>> Did that answer your question,
Councilor?
Other questions?
Councilor Oppenheimer.
>> Thank you, Mr. Chair. Uh thank you guys
for being here. Um
it's
good to have Gemini here as we're
talking about uh where we're going to
regulate. I got a lot of real specific
questions which I know you're not going
to be uh able to answer or going to be
end user questions. I'm going to ask
something just very general uh to give
you an opportunity. Outside of the
financial aspect, what are the benefits
to Sioux Falls of a data center being
built uh in this area?
>> So
I I guess to
clarify one point, I think those the
financial from the tax revenue does then
lead to other tangible benefits that
could come, whether it is reinvesting in
the community and that would be
something for the city to decide as far
as
uh being able to lower the tax burden on
the the community. There have been many
areas where I'm sure you've potentially
seen some of these stories where
it could be teachers receiving
significant bonuses because of these
types of projects. Um it could be
schools expanding and having much better
resources than they had before.
And you know, aside from that, I guess
sphere of tax revenue and what could be
done with the tax revenue, you know,
from just speaking to a lot of
businesses, a lot of stakeholders,
residents, I think one thing that's
happened from a lot of projects,
even
you know, it could be wind projects
where power is not necessarily being is
going out of the state and it's not
staying in the state. This is an
opportunity, I think, where
the state can benefit from the power
and from the data.
There are no borders to necessarily
electricity or data. They crosses
borders. So if
in in the case of Excel, if they were
not to use this power here, they could
easily
and move it to another state where it
would be used.
And here is an opportunity for the city
of Sioux Falls and the state to actually
benefit from the power from its own data
rather than allowing another state
because we'd still be utilizing those
resources. It's just another area would
be benefiting from them rather than the
the city and state itself.
>> Thank you.
One more? Go ahead, please. Yes.
>> The other question I had is can you give
us a an example of
a data center that has been built by
Gemini or that you have been involved in
that's been a big success that we can
look at as an example?
>> We don't have a fully operational data
center that we could point to right now
and
share with you. There's several projects
we're working on. A lot of our work
has been in the real estate space and
development, especially in the
industrial space.
And that's why we've also brought on a
lot of partners with data center
experience. But one thing to note, these
types of data centers, especially
probably the reason why we are having
this conversation are
are in some ways new. You know, data
centers that were built over the course
of the last 10 20 years aren't the same
as the ones that are being built now and
those are very unique. So there are a
lot of people on our team and a lot of
the individuals that we partner with who
have vast experience but under like the
Gemini name and
there is no one I could point to you and
share that info.
>> Thank you.
>> Committee members, any other questions?
I think the only question I have is
clarification.
Is it Is it fair to say that really the
next step in the process is a permit
application for a transmission line from
Excel to the PUC? That that that
That has That has to take place.
>> is That is definitely uh probably
the next major milestone
>> Okay.
>> would be to submit that.
>> And that is an Excel application. That
is not a Gemini application. Is that
correct?
>> That's correct.
>> Okay. Thank you.
>> Just so you're clear, they are asking us
for some information about our site
because it's connecting to us, but it's
completely driven by them.
>> Thank you so much. Thank you.
>> All right.
Thank you.
>> Committee members, we'll keep it here on
the topic of open committee discussion.
Anything that has come up tonight that
you want to ask our staff to dig into
deeper or anything you kind of want to
make sure to
uh get out on the table now as we
continue continue this process of
listening and learning.
Councilor Spelberg.
>> Thank you, Mr. Chair. I think one thing
that sticks out to me after the meeting
two weeks ago was just having
um security on the surety bond. And if
we've done that in a project in the city
in the past, this is obviously a larger
project than we've seen in the past. So
I think it's something important. I'm
glad the uh constituent brought that up.
So if we could look into that, that
would be great.
>> Great. Thank you.
Councilor Penkunan.
>> Yeah, I was sort of wondering the same
thing um and maybe just more general,
but on the along a similar topic is, you
know, what could be passed that would
run with the land, so to speak, if if we
know that um that we're you know, who
who gets this permit has a different end
user, what could be what would be tied
more with the parcel, so to speak?
Um is what I'm getting at because
if if um
if
a lot of requirements are are met by
the applicant, but then the applicant
isn't our long-term user here. I just
want to take that into consideration.
>> Okay, I just want to make sure I'm
understanding so that we can give
clarity to the staff and the attorney's
office on what we're looking for.
Attorney's office, feel like you got
clarity on understanding regulation, how
it passes from one ownership to the
next? Okay.
>> Yeah.
>> Thank you.
Councilor, anything else?
Go ahead, Councilor Oppenheimer.
>> Think it'll be useful to look at in some
detail at some of the examples that were
given
by Attorney Pfeifle, including Morton
County, Maricopa County, and
Pennsylvania, because seeing what
regulations were put in place there and
seeing what their effect was, because if
there's
solid regulations in other states and
other cities, rather than reinventing
the wheel, are there things that we can
learn from there? Were they too loose or
too tight in some areas? I think
doing some deeper diving into that would
be extreme.
And I love to give our attorney more
work to do.
>> Great. Any other questions?
Think for me, you know, two things that
really stand out. One is I
I think we got to make sure that we got
some sort of teeth in place. I think the
state has spoken clearly about this
utility issue and electricity issue, but
we've got to have some mechanism locally
that when a building permit is applied
for, that that utility agreement isn't
is in place. That that's not a Hey,
we'll discuss that later, because the
moment a building permit is issued, it
that's just we can't we can't be
changing rules after building permits
are issued. That's just more of a matter
of principle piece. So before that
permit's issued, we've got to make sure
that we get utility agreements in place,
and we got to determine what locally we
can require when requesting a building
permit on that on that front.
And so second thing, I mean, the noise
the noise piece is a
I think as I've been trying to I've been
trying to in my my work through like
what am I hearing the most from
constituents and things like that. I
think water and electricity's been
talked about a lot and we've seen
examples of that everywhere. The noise
peace has risen up of what I'm listening
to more frequently and just trying to
reach out to some communities and get
some more specific examples on the
things that the engineer over here
discussed cuz it's not something many of
us discuss every day just that we're
understanding that and we've got a
mechanism in place again. It all comes
down you can have a rule on the books
but what's our mechanism moving forward
of how we're watching that and managing
that moving forward. So that's a new
area that I plan on spending some time
on over the next month talking to
different communities specifically and
understanding kind of within that 3 mile
range what what takes place. Any other
final comments in the open discussion
period here?
At this time we'll turn it over to the
community members that are with us
tonight and have an opportunity for
public input. We thank you for being
here tonight and listening as well and
so this is opportunity for public input.
Speak to committee members you got 3
minutes each to come forward and speak
on any topic relating to the regulatory
oversight committee.
>> Thank you.
Okay.
[name redacted] if you can't hear me let
me know. My name is [name redacted] and I
live in Minnehaha County.
Okay there's some thoughts here mainly
for the public because I think you all
have pretty well made up your mind to do
this whether we like it or not.
So light industrial versus heavy
industrial
is this zone I last I heard this is zone
for light industrial. If that's the case
that's absolutely ridiculous.
My understanding is the low frequencies
that cause the health issues and
disturbance so that needs to be more
specifically studied
by experts outside experts.
Uh you quote the amount or somebody up
here quoted the amount of data centers
already in existence. I have not yet
heard the word once
hyper scale.
You talk about you, whoever's talked up
here, talks about yeah,
they have this data center there, they
have this data center there, but
which ones are hyper scale?
And that's what we're talking about,
hyper scale. That's very important to
keep that in mind.
Okay, Gemini da Gemini data center is
hyper scale.
Hyper scale data center does not bring
jobs in. They have their own specialized
crews that travel around and construct
these from beginning to end, very
specialized
project.
Then it takes a minimum crew, very
specialized, pre-trained crew to
maintain them, which they do not have
locally. I doubt it.
This doesn't only affect Sioux Falls, it
greatly affects the residents of Brandon
in Lincoln County.
They were not allowed to sign the
petition to get this on the ballot,
which we did, some of us did, out in
freezing weather where the ink was
freezing, etc. and given I think two
weeks, not very long to get it done.
Um one more thing, who's responsible? I
hear rumors. They're they're rumors, but
I hear rumors that some of these hyper
scale data centers last about five years
and then technology gets ahead and they
no longer are used. So if this happens,
who is responsible to completely
disassemble and restore that land to
what it was before that
hideous monster was built? Thank you for
your time.
>> Thank you.
Welcome.
>> Good evening, Mr. Chair, members of the
City Council. [name redacted] with the
Greater Sioux Falls Chamber of Commerce.
At the chamber, we want to ensure that
we're keeping regulatory certainty for
all industries in our city and state. We
we to see that South Dakota remains open
for business to all industries and make
sure that we remain transparent and fair
to all industries when we are creating
policy, which is important to ensuring
that we are not closing the door on
opportunities that could come up today
or some other time down the road. So
with that we'd just uh like to see
certainty and regular regulatory policy.
Thank you.
>> Thank you.
Welcome.
>> Thank you.
Thank uh [name redacted], Sioux Falls.
Um this is going to be a little bit of
tough love.
Uh I grew up in New York City. I lived
in the Bay Area for 14 years.
I know a little bit
>> I'm sorry. Can you just talk Lift the
mics up.
>> Oh, sorry.
>> Crowd wants to hear you, so please.
>> I grew up in New York City and lived in
the Bay Area for 14 years.
I know a little bit about the people on
the coasts.
I know a little bit about Wall Street
and Silicon Valley.
They're laughing at you.
They look down on South Dakota
and have nothing but contempt for South
Dakotans.
They think we're a bunch of rednecks and
morons and white supremacists.
I know this firsthand.
They think that they can con us into
lining their pockets by telling us that
South Dakota will be part of the AI
revolution.
They think that they can hoodwink us
into believing that we're going to
benefit economically and partake in the
wealth.
The City Council and Mayor are swimming
with sharks
and they don't seem to know it.
They're being played
and they don't seem to know it.
They're confirming the stereotype that
South Dakotans are unsophisticated and
not particularly bright.
If anyone here thinks that Wall Street
and Silicon Valley aren't going to end
up with all the money, I have a bridge
to sell you.
Again, they are laughing at you.
Sioux Falls uh there's been turnover in
the state legislature. It's widely
expected that another 50-year tax break
will come up for vote,
and this time it will pass.
There are indications that there will be
efforts to expand the tax breaks to
include no property taxes and no sales
taxes on electricity.
This won't be a surprise given that the
new state legislators' campaigns
were heavily funded by pro data center
PACs,
and they will do the bidding of their
masters.
Sioux Falls has enjoyed rapid growth in
a thriving economy. Our unemployment is
at 2%.
We're doing just fine as is.
The proposed hyperscale data center
could put an abrupt end to this and send
the city into reverse.
Property values will certainly decline.
Conferences and conventions have been
coming to Sioux Falls because it's a
city on the rise.
Organizations tend not to choose
declining cities for their conferences.
Why take this risk when the economy here
is already prospering?
This isn't a situation of a depressed
city trying to do something to improve a
weak economy.
If the city council and mayor allow this
hyperscale data center to be built
and the city suffers as a result,
the history books will contain the names
of the people who presided over this and
flagrantly disregarded the will of the
people.
Thank you.
>> Thank you.
Welcome.
>> Good evening, council. My name is [name redacted].
I'm a professional engineer with HR
Green and here in Sioux Falls. I live in
Sioux Falls. I'd also like to briefly
clarify that I'm not related to our
city's public works director, Mark
Cotter.
HR Green regularly provides engineering
consulting services to the city of Sioux
Falls for utility projects involving
water, sewer, and roads.
And HR Green conducted a planning study
for sewer service in northeast Sioux
Falls, so we are familiar with the
proposed development area. And in the
interest of transparency, HR Green has
been retained by Gemini
to design the water and sewer
infrastructure for this site.
HR Green places a high value on a
relationship with the city of Sioux
Falls as well as our relationships with
local developers. Our employees pride
themselves in building and strengthening
the communities where we live and work.
I'm not here to tell you whether we
should or should not have data centers,
uh but our engineering role is to design
infrastructure in accordance with the
local requirements.
I am here to speak to my company's
experience working with Gemini on the
infrastructure planning for the site.
Gemini has been professional to work
with, engaged in the land use amendment
amendment process and responsive to
comments throughout the review process.
Gemini has funded the water and sewer
engineering as part of the approval
process seeking the future land use
amendment
and they provided information that we
asked for and worked through city staff
comments in that process.
Uh I think that future land use
amendment process has been described by
others in in more detail. Um I can speak
to the that Gemini has committed that
the water service planned to the site is
limited to domestic use and the sewer
and pump station are sized to serve
future growth to the south, not just
this property.
Easements were also established as part
of that land use amendment and in that
way the city or Gemini has followed the
development process.
The project does have local economic
impact.
Gemini has employed local designers to
be involved with the project, not just
HR Green, my company.
Uh other local consultants have been
involved with survey, geotechnical and
utility planning
and additionally Gemini has been
discussing plans for the infrastructure
improvements with local contractors and
suppliers.
Finally, I'd encourage the committee to
consider what gives everyone confidence
over the long term.
Clear standards that protect residents
but also give anyone investing in Sioux
Falls a predictable set of rules. They
also guide the engineering process so we
know what to expect when designing
infrastructure to support developments.
At HR Green we are local consultants who
have been in Sioux Falls for years, and
we plan to be here for years to come.
Thank you.
>> Thank you.
Good evening.
>> Good evening. My name is [name redacted]. I
am the founder of [business name redacted]. Um
I just wanted to come up here and kind
of talk about some of the issues that
I've had um trying to to get [business name redacted]
brought into South Dakota and Sioux
Falls. And then we face a lot of similar
problems that data centers are having,
and it comes down to water, land, sound,
light,
uh pollution. And so we've been working
over the past three years to develop
solutions to those specific problems.
And it just so happens that the data
centers are facing these same problems.
And
so I'm just proposing that uh
you know, there are solutions to these
problems.
They might not be as publicly known as
the problems themselves, but
I think that uh
the solutions are there, and we would
like to be part of the conversation in
integrating controlled environment
agriculture farms to be consumers of the
waste product of the data centers
uh when it comes to
reallocating a lot of that heat, um
capitalizing on the heat generated from
the closed loop systems that were
discussed earlier, um and mitigating
some of the sound through ventilating
underground through these controlled
environment agriculture uh facilities
that would be connected to
the data centers um and have a symbiotic
relationship between the two,
solving the majority of the issues that
the public is having.
And that's all I have.
>> Thank you for being here.
Welcome.
>> Good evening, Council.
Thank you for the opportunity to speak
today.
My name is [name redacted].
I'm here with Century.
We do commercial and industrial
construction throughout the Midwest
with offices in Sioux Falls and
Watertown and and of 225 employees.
Over the last few years, we've been
forced to travel farther and farther
from home to keep everybody busy.
Our employees have spent more time on
the road and more nights away from their
families because that's where the work
has been.
We want to see more of that work come
here to Sioux Falls and to the state of
South Dakota.
Data center projects create
opportunities for businesses like ours
to keep our people working closer to
home,
hire and train new employees and buy
from local suppliers and subcontractors.
The impact reaches beyond the
construction site.
It supports restaurants, hotels, local
businesses,
and the families who depend on these
jobs.
When our people can work here, more of
those dollars stay in our communities.
I encourage this committee to recognize
what these projects mean for local
businesses and working families, help
create a path for them to move forward.
We have the people and the skills. We
want the opportunity to put them to work
here at home. Thank you.
>> Thank you.
Good evening.
>> Good evening, Chair and council members.
My name is [name redacted] and I'm a
resident of South Dakota. I am a
business agent for the Northern Midwest
Regional Council of Carpenters here in
Sioux Falls. We support future
responsible data center construction in
Sioux Falls
and must protect taxpayers and utility
ratepayers, respect neighboring
communities, create jobs, and delivering
lasting value
to the people who live here.
This should not be a choice between the
economic opportunity and community
protection.
Sioux Falls should insist on both
passing a
insist on both passing a moratorium is
easy. Developing responsible policy for
generational advancement in this
community for years to come.
We are confident that you that you as
elected officials will make that happen.
For our members, these projects
represent more than buildings. They
represent family, supporting paychecks
and opportunity to build careers close
to home.
We have over 250 members in our
organization and we have about 200 that
live right here in Sioux Falls.
A large multi-phase project could allow
apprentices
to work and learn at one location for
much of their apprenticeship.
That's opportunities for high school
students graduating in the upcoming
years to get into the trades and build
careers right here in Sioux Falls.
Combined with classroom instruction and
continually
could help prepare the next generation
of skilled workers. We urge the council
to remain committed to registered
apprenticeship, strong safety standards,
fair wages,
and benefits and opportunities for local
workers and qualified contractors.
The benefits should extend beyond the
job site.
Local hiring
local hiring and purchasing can help
construction dollars reach our
restaurants, stores, suppliers,
equipment providers, and other
businesses throughout the community.
Tax revenue must also be part of the
discussion.
Data centers pay applicable
taxes including taxes on energy
consumption.
Their investment could generate
substantial public revenue in the
millions of annual dollars.
Sustained revenue and responsible
management could help improve
infrastructure
and public services for generations of
Sioux Falls residents in the future.
We stand beside you welcoming developers
willing to invest in our workforce,
supporting local businesses,
and protecting our community.
Set high standards, enforce them, and
build a future that benefits the people
who who call Sioux Falls home. Thank
you.
>> Thank you.
Good evening.
>> Good evening, council members.
My name is [name redacted] and I'm the
business agent for UA Local 300
North and South Dakota.
Local 300 represents over 600 members
of highly trained
members in the plumbing, pipe fitting,
steam fitting, and HVACR service
industries.
I am here before you tonight to support
the proposed data center project
here in Sioux Falls.
Uh data center projects provide
thousands of work hours for our members
and family sustaining careers
with industry leading benefits.
Not only does the original construction
of a data center provide for this,
the maintenance, retrofitting of data
centers ensure consistent steady
employment
opportunities for us.
Uh we have the chance with this project
to create employment opportunities
and increase tax revenue for the
community.
Opposing this project only sends the
message that we're closed for business.
Stopping this project from moving
forward
does not stop other data centers from
being built.
All it does is ensure it's going to go
someplace else.
Thank you for your time and
consideration.
>> Thank you.
Welcome.
>> Hi.
Uh good evening council members. My name
is [name redacted].
Um I sent an email earlier today just
with some information about the East
River Developmental Organization who is
already um exploring planning on new
infrastructure for alternative domestic
water sources uh because the Big Sioux
aquifer is already near in capacity.
This is everyone's talking about right
now, jobs, opportunity. What about in 20
years, 30 years, 40 years, 50 years? Is
there going to be water for anybody to
drink, to do ag with? This is a real
concern.
And just a reminder that District 2,
Southeast Sioux Falls and Brandon has
already voted with a two-third majority
for candidates who oppose data center
development next to their homes. We were
not consulted ever.
Uh my main concern is that all current
regulations discussed here tonight were
not created with hyperscale data centers
in mind. I would argue that all light,
noise, water, and sound pollution
standards are too low for this industry.
Bottom line, whatever the current
standards are, they need to be
strengthened to reduce limits through
mitigation by 75%
to protect the public within the 5-mile
impact zone, mainly District 2.
Fundamentally, we don't want to see it,
we don't want to hear it, we don't want
to feel it. I don't want to breathe it.
We don't want to breathe polluted air,
drink polluted water, or pay any
increases in water or utility or
property tax or health impact costs. Mr.
Cotter, you stated that Gemini stated
they intend to have a closed-loop water
system end user. The word intend is not
appropriate. The closed-loop system
needs to be mandated to any future user.
They need to be mandated in in code to
uh prevent all types of pollution,
which is again why we need a 1-year
moratorium to discover best practices in
all categories to create regulations
that mandate best practices that protect
South Dakota citizens first and
particularly District 2 residents. The
civil engineer who spoke earlier stated
that there is no
regulatory standard nationally or state
for DBCs. This is not acceptable.
Low-frequency noise is a real medical
concern. The regulation and the
mitigation needs to be robust and it
needs to be clear.
My understanding is that Brandon School
District will receive property taxes. It
was also uh
stated that if these tax breaks go
through, all the money that everyone's
talking about is just going to go poof.
It's going to disappear. No electrical
money uh on utility rates, no property
taxes for any school districts. That's
that's a real concern that needs to be
codified and I want to know if you have
a plan for that. I want to know if
there's a legal avenue to prevent that
from happening.
At the end of the day, no one looks for
hyperscale data centers.
Uh they don't look for a hyperscale data
center community to move to or to live
in. South Dakota is fantastic. We don't
need this type of industry if it's not
done right. And I oppose and I would say
we don't need it at all.
>> Thank you.
>> professional
engineer with
with Infrastructure Design Group in
Sioux Falls.
Uh we're a local civil engineering and
land surveying firm.
Our company has been involved with
numerous developments
uh
throughout the city and the region. And
we did assist Gemini with the
preliminary planning, engineering, and
surveying for their property.
We were just one of the many engineering
firms working on this project.
I wanted to share a few observations
just from my experience working on this
project, but also offering an
engineering perspective on responsible
development in general and the
importance of having clear and
consistent regulations. So these do not
only apply to data centers.
First, our experience working with
Gemini and their team has been very
positive. They started off being very
inquisitive as they reviewed and learned
our local requirements.
They've been responsive, professional,
and willing to work through the
requirements and challenges that come
with developing property.
When issues were identified, they have
been willing to address them and follow
through on their commitments.
One concern typically expressed by
council members and the and the public
is whether the developers will follow
through on what they promise.
That's a legitimate concern and one that
applies to all types of development, not
just data centers.
In my experience, the best way to
address that concern is through clear
requirements and consistent enforcement.
We can also all be thankful our city
already has ordinances, engineering
standards, and development processes in
place to do exactly that.
I want to recognize our city staff. I've
been working with the city for over 20
years and I've lived here my entire
life. City staff has clearly clearly
communicated their requirements to
Gemini and the entire design team,
while also holding the project
accountable to those requirements.
They've enforced their standard and
required Gemini to follow ordinances,
standards, and processes currently in
place.
Gemini worked diligently with the city
to fulfill these requirements and work
through the city's standard processes.
That's exactly how the development
process should work.
Developers make significant investments
in land, infrastructure, planning,
engineering, and permitting based on the
requirements in place when they begin.
When those requirements change midway
through the process, it can create
substantial additional costs, delays,
and uncertainty even for projects that
have done everything asked of them.
Designs get redone, studies repeated,
schedules slip, and costs rise.
That certainly doesn't mean regulations
should never change. As new types of
development emerge, it's appropriate to
evaluate whether additional safeguards
are needed, which is the reason for this
committee
and this very meeting. I encourage the
committee to recognize the protections
already in place and build upon them
where necessary, listen to the feedback,
study what other cities are doing, and
carefully consider the impacts of
changing requirements for projects
already underway.
Thank you.
>> Welcome.
>> Hi there. I'm [name redacted]. I've spoken
with you before and sent you emails
before. Um
First correction, the problem with the
closed-loop water system flushing and
poisoning the
city is not Gillette, it was Cheyenne.
So don't look for Gillette Gillette for
answers. Um we have received I won't
call it misinformation but misleading
information tonight by people who know
better.
I'm referring to noise. And let me
explain how DBA and DBC noise bands
work. Consider you have 100 students and
they take a test. Let's say most of
them, almost all, score from 40 to 65.
They're not high achievers, but one of
them scores 100. So somebody asked,
well, what was the average score? Oh,
61. Okay, does that tell you anything
about the guy that scored
No. Well, that's how
DBC and DBA work. They take a huge band
of noise from low to high frequencies,
average them all into one number. So if
you have really loud infra noise at a
certain frequency band, it's totally
missed because it's all watered down in
the big number.
So that's why the whole DBA system,
which they've been referring to is fine,
is not fine. What we need and what I
sent you earlier, which is that's why I
just use the student analogy because
it's kind of hard to explain, but octave
band measurements take small bytes of
information like um a range of
of 40 to 60 hertz and measure that. 60
to 80 hertz, measure that. So then you
get in individual bytes of noise levels
and that way you can tell where is your
loud noise coming from. And that is not
going to be captured in DBA or DBC or
DBG because and they're all going to
miss a certain in between amount between
the very low frequencies and your DBA
and DBC which don't go so low.
They're designed to help protect people
from noise they hear and the infra infra
noise may not even be audible. It is
more felt. I also want to address the 75
decibel um
level that's acceptable at the
property line. I don't know if houses
abut this property line or not, but
infra noise, the low frequency noise
causes problems, health effects below 75
decibels.
Um it's recommended at no more than at
more than 40 decibels at night and 55
decibels during the day cause adverse
health effects. So if you're relying on
75 your and the houses are close to that
property line, you are going to have
unhappy property owners because they are
going to be affected by that noise.
Sleep deprivation, cardiovascular
effects,
possibly affecting the cognition in
children and so forth. And again, I I
think it is misleading for some of the
people to come up here and not explain
that to you.
Um
I also have specific information I can
provide to Councilman Pankonin about
specific equipment at specific hertz,
and I will send that to you.
>> Thank you for your feedback, and thank
you for correcting my earlier error on
Cheyenne. Thank you.
Welcome.
>> Hello. I'm [name redacted], and I live in
Sioux Falls. And as the city attorney
mentioned, data centers are a unique
industry, and they require a unique
approach. It sounds as if Gemini is here
tonight setting the stage for really no
meaningful regulations.
I hope the city takes into consideration
that this property, this industry that's
planning to come to our great city is in
the midst of hundreds and hundreds of
homes.
Therefore, the attorney's statement that
the primary role of the city council is
to protect the health and well-being of
the people
I I have to say I'm astounded that none
of the ordinances that we've talked
about today actually cover that.
So in relation to the characteristics of
this proposed project, I do believe that
an entire new body of ordinances and
management of them, as you know I've
said to you before, the monitoring and
the consequences need to be put in
place.
I think it's your primary primary role
to protect the health and well-being of
the people of Sioux Falls.
I appreciate all of the things that
they're talking about in terms of water
and power, but nobody has spoken today
about health. Nobody has spoken today
about environment. Nobody has spoken
today about the development of children.
Nobody has spoken today about
pollinators or about bird migration or
about
groundwater.
And as far as the dumping of chemicals,
um I'm astounded that that again, for
the second time in front of this
council, has been met with no answer.
And that happened in January as well.
Gemini was asked the same question. What
about dumping of the chemicals in the
closed loop? Well, we haven't thought
about that yet. And I heard the same
thing more or less again today. We are
not ready for this project.
Way way over our heads here. We are not
ready for this project. So I hope you
take that into consideration. I
appreciate all your time and effort for
these meetings and for inviting the
public. And I hope you take us into
consideration as we the people and what
our worries are with this. Thank you.
>> Thank you.
>> Good evening, ROC committee instead of
council.
Um my name is [name redacted]. I'm chair
of Let You Falls Vote and we back in
January collected 5,012
signatures during absolutely freezing
cold temperatures.
Um tonight we had heard a lot of
numbers, but what numbers we didn't hear
are the stats from regular citizens in
the community.
On November 3rd, voters across the
country weighed in on data center
development.
45 out of 47 data centers brought to the
ballot were voted out.
In May,
it was reported that 70% of Americans
opposed AI data centers being built in
their local area.
In August, University of Pennsylvania
survey found that 61%
opposed new data centers in their
communities, while only 14% had
supported them.
That that opposition has cross political
lines. Now while communities across the
country are raising concerns, Congress
is considering legislation that could
make it harder for
those same communities to challenge
major developments. It's called the
Bipartisan American Affordability and
Jobs Act, or BAHA.
This bill would speed up federal
permitting by changing environmental
review requirements. That means less
time spent reviewing potential
environmental impacts before certain
projects receive approval.
It'd also make some federal permits
harder to revoke or change once they're
issued. That means if problems are
discovered after approval, government
agencies could have less flexibility to
correct them.
And some provisions could limit when
courts can stop construction even after
finding problems with an environmental
review.
That means a project could potentially
continue moving forward while legal
challenges over environmental
protections are being resolved.
The bill also includes provisions
included to protect utility customers
from paying certain data center
infrastructure costs. Those protection
matter, too.
I want everyone to understand what's
happening. We're seeing widespread
public concern about the developments.
At the same time, lawmakers are
considering changes that could weaken
environmental oversight and legal
remedies.
So what does that mean for Sioux Falls?
We hear plenty about economic
development, private investment, keeping
our city attractive to businesses.
What we aren't hearing nearly enough
about
what people
Excuse me. What we aren't hearing nearly
enough about is what people who actually
live here want. You work for the people
of Sioux Falls, not for Gemini, not for
developers, and not for corporations.
Corporations have attorneys,
consultants, lobbyists, and entire teams
of experts representing their interests.
Ordinary residents don't have those
resources. They shouldn't have to become
experts in zoning, electrical
infrastructure, environmental science
just to have a meaningful voice in their
community. They certainly shouldn't be
expected to write the ordinances that
are supposed to protect them. That's the
responsibility of local government. I'm
not claiming national polling tells us
exactly how Sioux Falls residents feels
about Gemini.
That's why we should be asking them.
Economic development is supposed to be
benefit to the people who live here. The
people of Sioux Falls are not an
obstacle up to development. They are the
reason that local development
or local government exists in the first
place. Thank you.
>> Thank you.
Welcome.
>> Thank you.
My name is [name redacted]. I was born
and raised in Sioux Falls.
Thank you to the constituent who brought
up that it was Cheyenne, Wyoming instead
of Gillette, Wyoming. I also would like
to add that the research that I
did about that incident was that the
closed loop hyper-scale data center, the
construction of it um
caused
the developer, the the contractor,
excuse me, to dump over 800,000 gallons
of construction wastewater into
Cheyenne's public sewer system. Um the
average household in Sioux Falls uses
about 5,200 gallons of water per month.
I'm not a doctor, but it feels like
that's more than just a household use
for this data center.
Um while I'm grateful for the
opportunity to share my perspective, I'm
disappointed that we have to be here
tonight. I know that you know that
thousands of people throughout the
United States have reported negative
financial, environmental, and health
impacts as a result of living or working
near hyper-scale data centers. I know
that you're working to understand the
risks and how to mitigate them, and I
appreciate that. I know it's your job to
ensure that Sioux Falls area residents
are protected from reported effects such
as rising energy costs, water
contamination, noise, and air pollution,
everything we've talked about tonight.
I know that you know that this needs to
be done right so that future generations
don't bear the burden of your mistakes.
I am struggling to understand is why
we're scrambling to get this done so
quickly. It feels like I'm a student
again and we procrastinated and we just
have to cram to get things done
overnight.
From where I stand, it feels like Gemini
saw a blank slate and seized an
opportunity to take advantage of our
lack of preparedness. Um [name redacted]
from Gemini mentioned the investments
his company has made into the
infrastructure to support this project.
They got their foot in the door, but
that doesn't mean that we're required to
hold it open for them without putting
common sense protections in place. A
moratorium would be the most efficient
and logical way to proceed. This would
give the city time to establish adequate
protections and ensure that Gemini knows
the rules before investing more into the
area's infrastructure. A moratorium is
the only logical step forward. Thank
you.
>> Thank you.
Good evening.
>> Good evening, chairman and members of
the council. My name is [name redacted] and
I work for the South Dakota Chamber of
Commerce and Industry. I'd like to
extend the regrets of our CEO, [name redacted], who was unable to attend
tonight, but recognizes the importance
of this conversation.
While my professional life centers
around advocating for a strong business
climate in South Dakota, tonight I'm
here in a personal capacity as a proud
citizen of Sioux Falls who cares deeply
about our community's future.
I've been thinking about lately that
resentment grows from the things people
never tell us,
and assumptions grow from the questions
we never ask.
And when we leave those spaces empty,
human nature has a funny way of filling
them in with the worst possible
explanation.
They say that misery loves company.
Well, I have always much preferred the
company of possibility.
And I believe Sioux Falls has an
extraordinary amount of possibility
ahead of it.
Last week I heard the mayor of Lennox
say when you have a seat at the table,
remember the most important voice is
never your own.
It's the voice of the people you're
representing. So tonight I'd love for
you to hear these voices.
The voice of contractors who see crews
they can put to work, and entrepreneurs
whose dreams become more achievable when
our economy grows.
And the voice of the taxpayer who would
welcome new businesses
hoping helping to shoulder the costs of
the community we all enjoy.
And the voices of our schools, family,
and future workforce
who stand to benefit when responsible
economic development strengthens our tax
base and creates opportunity.
And the voice of the young person
deciding whether Sioux Falls is a place
to build a career, raise a family, and
dream big.
Asking hard questions about data centers
is not only reasonable, it's necessary.
Water, energy, infrastructure,
and long-term community benefits deserve
thoughtful answers. But there's a
difference between asking a question
asking questions to understand an
opportunity
and closing the door before the before
the questions can be answered. And
there's a difference between protecting
our community from what we don't know
and preventing our community from
discovering what it could be.
I believe Sioux Falls Sioux Falls do
both, protect what makes us special
while embrace what's makes us stronger.
Thank you for being willing to have
difficult conversations and make
difficult decisions. Leadership isn't
about finding the path with least
criticism.
It's about having the courage to
consider what serves a community's
future.
Sioux Falls didn't become the city we
love by assuming the worst of what's
next.
We became this city because generations
before us believed in what it could be.
And let's be worthy of that same
optimism. Thank you.
>> Thank you.
Good evening.
>> Good evening everybody.
My name is [name redacted] and I am one
of just over 350 residential homeowners
out in the bluffs of Brandon.
We house almost 1,000 residents. It's
booming and growing.
The Gemini Data Center is going to be
located less than 1 mile from my home.
In our own district, senators and city
council members left us out in the dark,
so we're sadly fighting this after what
feels like is really too late.
[passage omitted for privacy]
But I'm really coming here to
relay what my really what my
what my high school best friend [name redacted]
said to me over the past 6 months. She
lives in Smithfield, Missouri. She is
just over 2 miles from what started as
not one but is now three data centers.
It started as a rural neighborhood
similar to ours and is now considered a
heavy industrial neighborhood.
We've been in talks again over the last
6 months and she's given me these
talking points and really just said
whatever you can do, fight with all your
might. She said they had 6:00 a.m. wake
up calls 7 days a week for 2 to 3 years
straight.
There's been horrendous traffic,
multiple accidents due to the hundreds
of construction vehicles going in and
out of the sites.
The low frequency sound
goes through their windows and their
walls that you can't unhear.
She can no longer walk their dog outside
for long periods of time.
[passage omitted for privacy]
So my asks are, has a third party
traffic study been done on Rice Street?
Who would be financially responsible for
road damage, ongoing maintenance and
traffic control?
Has a low frequency noise study been
completed for homes within three
quarters of a mile away?
And then my asks when you go down to
Nebraska later this week, I would just
ask you to see if there are residents
that live within a mile and see how this
is impacted their daily lives. And then
ultimately, would you want this in your
own backyard?
And then finally, I'd ask that you just
take our small but mighty neighborhood
into account and implement a moratorium
to collect more scientific data. Thank
you.
>> Thank you.
Welcome.
>> Hi. Um, good evening. My name's [name redacted]. I live in Sioux Falls. Um, we
understand that data now is the new
currency and power for government
corporations like they can get all this
information off of us and use it against
us or convince us to buy things that we
don't really need to be spending our
money on. So I'm curious how much more
money, you know, data, even our privacy
that the government and corporations
need. What's another data center going
to do for us individual citizens? [name redacted] was asked what how is it going to
benefit the city of Sioux Falls? I'd
like to know how do each citizen get
benefited by having another data center
come in, a hyper scale one?
How do we benefit as citizens? So I
think we're being taken advantage of and
the government and corporations like
don't give a damn.
>> Thank Thank you.
Welcome.
>> Hello. My name is [name redacted] and I've
lived in Sioux Falls for 65 years.
Um,
and I want to thank everybody for the
information tonight. I mean, it's great
information. It's it's more than I've
heard in when I sit in all these
meetings.
So I appreciate all of that
However, I have like 16 pages of
additional concerns that I have never
heard addressed.
And you know it's down to the to the
level of
will Gemini be required to shut
slow down their electrical use if we
have some reason that you know like like
in the summer when there's an excess use
or what is the oversight going to be?
Once they're up and running is there
going to be oversight and how is that
going to be handled?
There's what happens to the water after
it leaves? I mean we've talked there's
been a little bit of talk about that but
there's so many things that haven't been
considered and I know you have all these
cuz [name redacted] sent it to you.
So I just I hope you're looking at all
the details
and thinking through all of those
things. The devil's in the details and I
don't know that
that all the details are being
considered.
They may be in some of the forms that
were linked in that document but I don't
know.
But it and it was mentioned that the tax
money would go to schools and that type
of thing or could
traditionally that doesn't happen. I
mean we're still the lowest paid
one of the lowest paid states for
teachers and so if you could promise
that maybe that would help but you know
I'm not I don't have any faith in that.
And I'm just going to mention that I
this isn't impact to me. I live in the
middle of town. In fact I live on the
same street as director Cotter so I'm
not going to be impacted at all.
However, a lot of my neighbors and I and
as I said
or a lot of the people I know and as I
said I love Sioux Falls. I've lived here
my whole life and I don't want to see us
take this path of destruction that we
don't even understand.
So I'm going to ask that you remember
that you work for us and that
you vote with the people and not the
corporations and the best way to do that
is to have a moratorium until you study
the devil in the details. Thank you.
>> Thank you.
>> Good evening.
>> How are you?
Um forgive me if I shake. My name is
[name redacted] and I live in Sioux Falls um
in the avenue.
Um I wanted to play something
that I hope can go into the record if I
can get it to play.
This is um from a
data center in Southwest Michigan.
It will come in a second.
>> local examples of what it's like when
they're up and running.
One of the most common areas of concern
I hear about is the noise that they
could admit.
But one community in Southwest Michigan
has been experiencing the reality of a
data center next door for a couple of
years now. And they say the sound has
changed their lives.
>> Here's the sound.
Can everybody hear that?
>> Can you face the microphone, please?
Talk into the mic.
>> Pardon?
>> Just talk into the microphone, please.
>> sorry.
Uh if everybody heard that, apparently
they're experiencing this all day.
Oh, I'm sorry. Let me see if I can
>> you Ma'am, ma'am.
>> a few other things. I wanted to talk
about e-waste especially and PFAs.
Nobody's talked about forever chemicals.
Um forever chemicals have been found
this year in the Big Sioux River. And
they've been found in some wells in the
state of South Dakota.
And um PFAs are also a part of data
centers um because they're used to coat
I don't know a whole lot about the
electronics, but I know they're used to
coat um
I don't know if it's the connectors, the
wires, something like that you know to
keep the heat down. Um 10 different PFA
manufacturers are increasing their
production because of all the data
centers that have been built.
Um and it's very dangerous for children
and babies especially.
[passage omitted for privacy]
this is all I and all the research I've
done for data centers I've not found
anything that feels positive to me about
this. It seems like it's power and money
and that really bothers me. And the
environmental damages all there are a
lot of harms that go beyond the property
lines of the data centers. Why isn't
anybody doing an environmental impact
study? I don't understand why that
hasn't happened. Um, we've had so many
experiences from uh, data centers that
have gone across the country that didn't
come right. There was one in New Jersey
had a $5,000
I'm sorry, 5,000 gallon diesel fuel
discharge into a tributary that went to
the Meadowlands.
Is that my time? Okay.
>> Thank you for your testimony.
>> welcome.
>> Good evening.
Good evening.
Uh, members of the committee, my
neighbors, I'm here to speaking as a
private citizen. I'm here speaking as my
for myself and my own personal views.
We all know the public debate happening
across Sioux Falls right now. Since they
are asking you all to go ahead and put a
moratorium of one or two years on
the you guys are been reluctant about
doing an outright freeze to stall
economic growth and that makes perfect
sense. I give [name redacted] a lot of credit
for bringing one of my major points to
the table today was that if we waited to
pass ordinance changes in 2027, they'll
just go ahead and grandfather the rights
in on 2026's bill and go ahead and use
those and then hold that situation up in
court to move on to and and go under
those rules.
I think there's another way. I think you
can go ahead and do what's something
called a a good neighbor development
agreement.
For anyone unfamiliar with the term,
it's this is not an anti-hurdle growth
or not a growth hurdle. It is a
collaborative binding contract where the
city and a developer sit down before a
single shovel hits the ground to put
mutual commitments in writing.
I think of it as informal handshake with
paper teeth.
The city grants access to municipal
infrastructure resource protections and
site approvals,
and in exchange the developer
voluntarily agrees to clear enforceable
guard rails.
Approvals are not given without that
agreement.
These handshakes have had success in
Lancaster P PA.
The agreement included water usage caps,
sound attenuated enclosures, and clean
energy contributions.
In Cedar Rapids, Iowa, it contained
water conservation baselines, strict
noise limits, and municipal
infrastructure guarantees.
When this developer of an uh of other
volun sorry, with this developer or any
other voluntarily puts its signature on
agreement,
it completely bypasses the legal
the legal fight over grandfather
loopholes
and gives the city council a clear,
defensible instrument to to approve it.
Some of the things that you could put in
that agreement would be a one uh point
one to two and a half million dollar
escrow account requiring to pay fees if
they were to go above the abilities that
they were or as [name redacted] was saying
earlier that he was concerned that there
was not going to be any enforcement
mechanisms.
Um you can also say with the city state
of South Dakota will
basically allow sales tax rebates on a
lot of the purchases. You can require
them to go back in and reinvest those
sales taxes back into the community
without just for the same dollar amount
as the rebate themselves.
Um we've made lots of talk about the
water and and uh power issues. I would
also argue that one of my biggest things
would be that every five years as
technology advances, the technology to
uh muddle the noise to take care of the
water will increase and every five years
we should look back and and force the
data center to make those changes if
they're required to and help it be safer
for this community moving forward.
Um
for a long time the story of the hype of
scale data centers and heavy industrial
builds.
>> Thank you for your testimony tonight.
Welcome.
>> [name redacted], uh Sioux Falls homeowner.
Uh
these data centers have concerned me for
some time. Um
they're talking about the decibel
rating. We know that sound is hideous
sound. If you had to listen to that all
the time it soon drive you away.
And I was looking at your sheet it talks
about uh
the sounds that levels that are
acceptable.
From what I understand 85 decibels can
cause hearing loss over extended periods
of time.
Uh it says here that it can go up to 95
decibels
and pulsive sound and that doesn't
really define what a pulsive sound is.
Is that like a gunshot or can that be 15
minutes of time every hour?
And um
and 85
decibel can cause hearing loss.
Since it's exponential
uh 95 decibels is 10 times as loud.
So you can imagine having to deal with
that even on an intermittent basis would
drive you crazy.
Um
they talked about end user. I'm not
exactly sure what they mean by that but
to me it seems like they're going to
build this facility and then turn around
and sell it to the highest bidder.
Whether that's Microsoft, Amazon,
Google, NVIDIA, or Oracle, or whoever.
Uh so they're just going to turn around
and sell. It's easier probably for a
small smaller company to put this in an
area.
It doesn't cause as much uh
uh reaction as a large company would.
Uh so I think that's what's in the
making and uh
and then the the thing that I'm
concerned about is is the data use. What
kind of data do they really collect and
how is it used?
I understand Sioux Falls has authorized
the use of these flock cameras.
And we know that
that Edwin Snowden, he revealed that
everything we do, where we go, what we
say
and
is always recorded.
And my concern, one of my concerns is at
these data centers are we going to
record that information basically
forever. They can go back to this
information. Who wants to be tracked at
every turn?
We do have those those uh like I said
flock cameras and other ways of
of every time you carry around a cell
phone, they have ways of tracking where
you are. And they need a huge amount of
data centers
to record all that information. And
basically
we become a prisoner in our own country
because we've lost our
our freedom of uh
uh uh
privacy. The
>> Thank you.
>> The the the Fourth Amendment is
something I hold dear.
>> Thank you for your testimony.
Welcome.
>> Hi, good good evening councilors. My
name is [name redacted]. I'm a principal
with Gemini and uh I just wanted to say
thank you for having us. I want to
reiterate that we are 100% committed to
responsible development. Development is
it's a long, arduous, complex, highly
technical process. I've been in the
industry for the in the industry for the
majority of my career. Um and I just
want to reiterate, there is a ton of
detail. We are committed to uncovering
that detail, working with the best of
the best experts. Really good developers
bring along teams that are really good
at what they do. Uh, council member
Oppenheimer, you asked earlier if we'd
committed a or if we have completed a
data center before. We have not, but
we've developed a lot of projects. And
what you learn when you develop a lot of
development projects is you're the
quarterback. You got to put a really
really good team in place, and we have
that. And part and parcel with that is
communicating with local leadership,
with hearing from stakeholders. And I
just want to say, you know, I'm a
father, I'm a husband, I have children
as well. I would never build anything
that I wouldn't put in my own backyard.
And so I just hopefully my words today
can give some comfort to some of the
citizens here. We're committed to
working with you all, and we uh thank
you for having us.
>> Thank you.
>> Welcome.
>> Hello, [name redacted] from Sioux Falls.
I can't help notice just uh handful of
people coming up here, and it seems like
there's probably a lot of people in
Sioux Falls that are either in some type
of construction business, own one, know
somebody,
brother's, cousin's, nephew of a
business, and
they come up here and
want this because it's, you know, it's
going to be a massive project. It's
biggest one probably ever.
And I can't help but wonder why there's
an assumption that a single dime of that
money is going to be used to hire
anybody in Sioux Falls to do it, like
why that assumption's there. So I'm kind
of speaking to everybody in the room on
this, but it's good for you guys to know
too that
it's all about the lowest bid.
I don't even have any experience in
anything like this, but there's a really
good chance there's going to be a giant
company that's at a national level
that possibly may already have the bid
to put every single last
worker on site, and none of them are in
Sioux Falls.
They're not they're possibly might not
be a single
worker from Sioux Falls doing anything
on that construction site. I don't know.
I just noticed what's his face's choice
of words at the beginning was is we hope
to work with
whoever in Sioux Falls.
You know, if we can do that, that's a
good choice of wording because that
means that
if the if the bid's not there to come in
the lower price than the next guy, then
it might not happen.
In terms of my thoughts for
just learning more about this, I think
one of you mentioned it earlier where I
think since none of us really know a
whole lot about what we need to know and
we're all asking questions including
everybody
up here,
I would probably spend more time
actually just reaching out to any city
council members of just any community
that's already has one.
They already have all the answers,
whether they're good or bad.
You know, he mentioned and I believe
when you said that data centers from,
you know, 10 years ago are obviously
going to be completely different in some
regards than ones now.
So I guess the best
thing that I can think of off the top of
my head is maybe find a community that
has a massive data center that's like a
year old or two years old
that's been fully operational that would
be most similar to
what this one's going to be.
And they already have all the answers of
what's good and what's bad.
And somebody's comment earlier about the
taxes too since that appears to be the
only guaranteed revenue, period,
is if some if somebody above your guys'
head can pull the plug on that where it
really doesn't matter anymore,
then it essentially won't benefit us at
all if that actually happened.
>> Thank you.
>> Welcome.
>> Thank you.
Can you guys hear me okay?
All right.
[name redacted] I live in Lincoln County
and I'm
retired.
Um, just a couple things. Uh, first of
all, I agree with what [name redacted] said. So
that's one thing that'll save a lot of
time.
Um, a couple things that are a little
disconcerting.
Uh, at the federal level, there are no
regulations for data centers, especially
hyper
data centers. If they are, they're
minimal. And why is that? Because right
now there's a lot of money to be made
because there's no regulations.
And probably the biggest one I would be
looking for is how many hyper data
centers do we need? Regardless of one if
one is in Sioux Falls, how many do we
really need?
Um, and then the other thing is uh
I appreciate Gemini being honest that
they've
had projects, but they don't have a
fully operational uh data center yet.
And it's just a little disconcerting.
Um, not to say that they're not trying
to do the right thing and trying to
trying to do it the right way, but
again, they don't have any fully
operational data centers for us to
compare to.
And then um
the other thing is I haven't heard any
discussions about uh the backup
generators that are typically diesel
generators. And so if you could please
include that in your
reviews.
Um,
and let's see. Oh, the other thing is
the information of the guidelines about
the uh Pennsylvania that Pennsylvania
put out. I think those guidelines look
like they're good, but my question is
have any of them been fully implemented
in any of the cities yet?
And then um also concerned about uh and
this has been brought up a little bit
and I don't have any specific examples.
Well, that's a lie. I'm thinking of one,
but I won't say it.
Um, but conflicts of interest. Um, there
was a lot of data center money put into
the uh recent um
uh whatever. And uh I guess that's just
disconcerting. And what does that mean
to us?
And um also there's just something I
will just stop over and say to the
Gemini people because I really don't
want to say that online either. So thank
you.
>> All right. Thank you.
Welcome.
>> Um thank you. My name is [name redacted] and
I've
>> Can you step forward?
>> I thought all the information we heard
today was really good um both about
Gemini and the opposing of it.
Um I just want to express my
disappointment.
I feel like
our city council got the cart before the
horse.
You approved
rezoning before you really knew
how you should zone
uh hyperscale data center.
You've
neglected to put
things in place before permitting
was already issued.
They talked already that they've had uh
meetings with our developing
uh
governing bodies in Sioux Falls.
Yet
none of you thought
maybe
we should get all of this stuff in place
first
instead of
just moving forward and now we're trying
to back pedal to figure out how to make
this work. On top of it
it's 140 acres.
You put it in people's backyard.
There's people that are have homes that
they've invested in
and
worked hard to build
and they're a half a mile away from this
place.
I mean of all the land in this
surrounding area
that was the best choice.
I just I'm really disappointed
that there wasn't more
thought before you went and gave a stamp
of approval.
>> Thank you.
Any following Nope, one more.
Welcome.
>> [name redacted], retired IBW Union electoral
worker.
I've worked on Amazon. I've worked on
data centers.
I've been in Kansas City.
Where are they?
You can go look.
How many houses are by those places?
Take a look.
There ain't nothing around.
What's Amazon got?
Swans.
A
Ain't nothing up there.
There's no homes there. You guys would
buy one?
>> Can we talk into the talk into the mic,
please?
>> will.
>> Thanks.
>> You guys would buy one?
I built ADP.
I was up there, 38 across from DOT.
What's up there?
Ain't nothing up there.
There's no residential.
It's my wife.
She spoke what should be. We're like
three quarters of a mile away from this
place.
Just bought it.
And many more houses on the bluffs.
This is what we got to put up with.
You guys sold us out.
She's right.
Should have had it set before these guys
came in.
All this is a dog and pony show.
>> Thank you for your feedback.
Welcome.
>> Thank you.
I just want to say 73%
of people don't want these in their
backyards.
You know, I could care what we might
gain out of this. We might get some
property tax reduction. What's that
going to do to my home value if my home
value goes down 25 to 50%? I could care
less about a reduction maybe in property
taxes. There's just all of these people
from the bluffs and Pine Lake Hills, all
of these people that are close to this
Gemini site. They can't even vote for a
mayor or a city council because they're
not within that area, not within the
right area of the city.
So, um I just want to say it's never too
late to do the right thing. You could
always do a moratorium, give it more
time, make sure we're doing the right
thing.
>> Thank you.
Oh.
Thank you for being here this evening
and attending the regulatory oversight
committee. Our next meeting will be on
Monday, November 30th, and you can reach
out to committee members or city
councilors by going to the
siouxfalls.gov regulatory oversight
committee page there, and I appreciate
your time tonight. And therefore, this
meeting is adjourned.