County Square Redevelopment

At a glance

  • What: Joint City and County redevelopment of the County Square site, including roads, utilities, a City parking garage, townhomes and a planned grocery store.
  • Where it stands: Update presented at the August 24, 2026 work session; no vote.
  • Next: City garage expected spring 2027; initial townhome occupancy expected second quarter 2027.

Work session update (August 24, 2026)

  • Michael Frixen, Interim Planning Director, gave a timeline from 2020 to 2026 and described internal roadway and utility work, platting and road name changes, final development plan approvals and active letters of intent.
  • The City's parking garage is expected to finish in spring 2027. City Manager Lavrin said it will have about 380 spaces and no debt.
  • The Solaire Townhomes expect initial occupancy in the second quarter of 2027.
  • Joe Kernell, Greenville County Administrator, said Whole Foods will begin development when other projects begin theirs.
  • Mayor White said the Halprin Plan is reflected in the redevelopment and suggested planting trees as early as possible to get a jump on growth.

Sources

Log

2026-08-24 - City Council Work Session

Update from staff and the County Administrator; no action.