Southeast Stark Street 111th to 151st Safety Project
At a glance
What: Authority to acquire temporary construction easements for enhanced pedestrian crossings along Southeast Stark Street from 111th to 151st.
Where it stands: Public Works Committee referred it to Council with a recommendation to pass on September 22, 2026 (4 ayes, 1 absent). Design continues through summer 2027; construction is targeted for spring 2028.
2026-09-22 - Public Works Committee - Smith urged phone outreach to older property owners; staff said the process takes nine months or more and the City has avoided condemnation trials.