Cleveland Public Power Interconnection Rules
At a glance
Built from the official City Council minutes of April 6, May 11 and May 18, 2026. The newest minutes posted are May 18; every Council meeting after that has an agenda only, and no committee minutes are posted since April, so anything that happened after May 18 is not in this page.
- What: Three emergency ordinances introduced May 11, 2026 rewrite the rules for connecting private generation to the Division of Cleveland Public Power's electric system.
- Where it stands: All three were read and referred to administrative review on May 11, 2026. No later action appears in the minutes.
- Next: Committee review; check later agendas.
Detail
- Ordinance 587-2026 amends Section 523.25 (Interconnection Service for Distributed Generation), last amended by Ordinance 1662-09 of December 7, 2009.
- Ordinance 588-2026 amends Section 523.26 (net metering service), also last amended in 2009.
- Ordinance 621-2026 enacts a new Section 523.252 on interconnection into Cleveland Public Power's system by qualifying facilities, eligible large commercial customers and eligible large industrial customers, and authorizes related agreements.
- Related: Landfill Solar Arrays.
Sources
- City Council minutes, May 11, 2026: https://cityofcleveland.legistar1.com/cityofcleveland/meetings/2026/5/3859_M_City_Council_26-05-11_Meeting_Minutes.pdf
- Utilities Committee agenda, November 5, 2026: https://cityofcleveland.legistar.com/View.ashx?M=A&ID=1460885&GUID=1CCE38DA-F983-41E7-8F26-8E2FCBF2B065
Log
2026-05-11 - City Council
First reading of all three; referred to administrative review.
2026-11-05 - Utilities Committee
Ordinance 1171-2026, a separate Cleveland Public Power ordinance amending Chapter 523 (definitions, small non-building facility rates, joint registration), is on the agenda for discussion only.
- 2026-11-12 - Utilities Committee - Ordinance 1171-2026 (Chapter 523) returns to committee after the November 5 discussion.