Memorial Field final design and permitting

At a glance

Based on auto-generated captions; names and numbers may be misheard.

  • What: resolution appropriating $1.2 million for final design and permitting of the Memorial Field complex, funded by $600,000 of city bonds and notes and a $600,000 donation from the Concord School District.
  • Where it stands: approved on a roll call vote of 12-3 on October 13, 2026 (opposed: Horne, Schultz, Brown).
  • Next: design and permitting runs about 12 months, then a construction decision. Several councilors said they will not appropriate more until a written agreement (MOU) with the school district settles cost sharing, control and revenue.

The project

  • Joint city and Concord School District committee recommended rebuilding the fields in place to fix long-running drainage failures, with new track and field surfaces, lighting and fencing, and about 55 added parking spaces.
  • Estimated total about $22 million (down from earlier figures of $36-38 million); phase one (fields and track) roughly $13 million plus, with about $5 million for buildings that may never be built.
  • The $1.2 million is a not-to-exceed amount; David Gill said the goal is to come in under it. Design is needed to compete for Land and Water Conservation (up to $1 million) and Outdoor Legacy (up to a $15 million project) grants, each with a one-to-one match.
  • Timeline: about 12 months of design, then bidding and a 12-month build; realistically 2028 to 2029.
  • Alternative money named by the city manager: recreation reserve about $529,600 uncommitted, impact fees about $86,000 uncommitted, and about $140,000 expected left from the bleacher removal appropriation. Bonding is the traditional approach; using reserves reduces flexibility in next year's budget.

Public hearing (October 13)

  • Roughly 20 speakers over more than two hours.
  • For: youth lacrosse and football organizers, coaches, parents, the high school athletic director, a local contractor and students described an unusable track, drainage, injuries, no bleachers, rented lights and games and a senior night held outside Concord.
  • Concerns: no written agreement yet on who pays what ("cart before the horse"), whether to bond or use surplus, a competitive bid for the design contract, turf versus grass, and whether the city has approved the footprint.
  • Penacook and Merrimack Valley school district residents, including two school board members speaking as private citizens, asked for a split other than 50/50, pointing to district usage data (for example 88% of varsity football hours), a petition of roughly 600 to 670 signatures asking Concord School District to pay all construction costs, and higher need in Penacook.
  • The mayor apologized to anyone offended by a remark to an earlier witness.

Council debate and vote

  • Supporters said the field is unsafe and past due, the school district's check is a good-faith first step, and the council keeps full control of the decision on later phases: Kurtz, Fennessy, Todd, Foote, Keach, Schlosser, Sekou. Davie and Kalob voted yes reluctantly.
  • Common conditions: a written MOU before any further appropriation; Davie does not expect to support a 50/50 construction split; Kalob wants grant specifics, a capital campaign and public-private options.
  • Opposed: Horne (tax burden, debt service, unanswered ownership and control questions, Penacook fairness), Schultz (tax fairness) and Brown (wants the MOU and a competitive bid first; suggested making the golf fund an enterprise fund again).
  • Procedure: motion to move the question, a disputed voice vote, a successful motion to reconsider, then a roll call. The captions do not show a separate vote on paying from reserves instead of bonding.

Open questions

  • Share of construction cost between city and school district, and what control or revenue the district gets.
  • Turf versus natural grass; usage tracking by group continues through 2026.
  • Whether the design work is put out for competitive proposals.

Sources

Discussion time

About 201 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-13 - City Council 201

Log

  • 2026-10-13 - City Council - Public hearing and action. Resolution for $1.2 million design and permitting ($600,000 bonds, $600,000 school district donation) approved on a roll call vote of 12-3 after about 3 hours 20 minutes of hearing and debate.