Pelham Boulevard Reconstruction Assessment (RES 26-240)
At a glance
Based on uploaded (human-made) captions; staff names are partly garbled, so staff are identified by role.
- What: ratifying the special assessment for the Pelham Boulevard (Franklin to Mississippi River Boulevard) reconstruction, part of the 2026 streets and sales tax program.
- Where it stands: ratified 7-0 on 2026-10-14 after a hearing with mostly opposing testimony.
- Next: individual owners may appeal; council said the policy may be reviewed.
The project
- Road narrowed from 32 to 24 feet, an off-street bike lane, raised bike crossings, a 14-foot road shift to save large trees (about 160 of 202 boulevard trees kept), new lighting and sewer work, and tighter driveways under the parkway ordinance.
- Assessments total just under 12% of cost, below the 25% starting point, because many properties hit the special benefit cap.
Concerns raised
- Homeowners objected to assessments from about $8,300 to over $14,000, citing removed mature trees, lost parking, and no clear property value benefit.
- Owners said the special benefit analysis was opaque and relied on older sales data; an attorney for two commercial owners argued the generalized method is arbitrary under state court rulings and asked for removal or reduction.
- Council members thanked staff, called the policy a choice that can be reconsidered, and found no extenuating circumstances.
Sources
- 2026-10-14 - City Council (uploaded captions)
- https://stpaul.legistar.com/Calendar.aspx
Log
- 2026-10-14 - City Council - Staff report, opposing testimony from owners; assessment ratified 7-0.