What: the decommissioning plan, cost estimate and bond required by the Planning Board's site plan and stormwater approval for a completed solar field on Riverland Street, near the town transfer station.
Where it stands: accepted unanimously on 2026-11-09 after a continuance from the October 26 meeting.
Next: the project is going through final testing and a few punch list items before close-out and a certificate of occupancy.
Details
Staff said the estimate was reviewed by the Board's peer reviewer, includes a 25 percent cushion, and is to be re-estimated about every five years; the plan and bond were reviewed by town counsel. The bond is meant to continue indefinitely and be renewed as needed.