What: the planned community center and the Community Center Committee's work.
Where it stands: A committee update with slides is on the 2026-11-05 Select Board agenda. The committee timeline shows a 2025 revised charge of about 18 months, a fairgrounds access road agreement approved in July 2026 and capital-campaign preparation from January to October 2026. A Town Meeting easement action is needed.
Next: committee update on Nov 5; committee met 2026-11-10 (video).
Details
Timeline details come from the Nov 5 agenda and the committee's 2026 timeline slide; they were not checked against minutes.
Committee update on its phase three charge; no decisions. An RFP for the next design phase is expected at a future meeting; the charge ends around April.