Biological Nutrient Removal Project
At a glance
Based on auto-generated captions; details may be misheard.
- What: A biological nutrient removal and odor control upgrade at the wastewater plant.
- Where it stands: About 65 percent complete; $387 million budget approved March 2024 with no additional funding requested; 13 more staff being hired.
Log
- 2026-09-22 - City Council Workshop - Update presented in the workshop.
From the video (2026-10-27)
2026-10-27 - City Council Workshop: On schedule, substantial completion targeted for late next year; a biogas public-private partnership expected before year-end.