Transportation Investment Projects Fall 2026

At a glance

  • What: Staff updates on road, interchange, trail and right-of-way projects, including the transportation investment program bands.
  • Where it stands: Update presented 2026-11-10 (agenda item carried from October 27): 19th Street flood abatement about 75 percent complete; interchange and spiderweb projects targeting spring; right-of-way underway on Steam Mill Road, Whitesville Road and a roundabout; South Lumpkin Road preliminary plans due in January.
  • Next: Staff to follow up with the state on interchange signals and lighting and to label slides as state-managed or city-managed.

Details

  • Councilors raised signal and lighting concerns at a new interchange and a possible future signal at another interchange exit.
  • Northstar Drive roundabout paving was delayed from the originally announced dates.

Sources

Log

2026-11-10 - City Council

  • Staff update on construction, right-of-way and planning phases; councilors asked about signals, lighting and the Northstar Drive paving date.