Shore Acres Resiliency Project

At a glance

  • What: Early equipment procurement for the Shore Acres Resiliency Infrastructure Project: a $9,664,855.76 Guaranteed Maximum Price from Ric-Man Construction Florida, Inc.
  • Where it stands: Resolution 2026-166 approved April 16, 2026, 7-0 with Floyd absent.

Detail

  • Moved by Harting, seconded by Gabbard. GMP Proposal No. 1 dated March 19, 2026 is added to the Construction Manager at Risk agreement.
  • Supplemental appropriation of $1,000,000 from the Stormwater Drainage Capital Projects Fund (4013) to the Connecticut Ave NE and vicinity resiliency project (19207) for the GMP, engineering project management, contingency and soft costs.
  • Brejesh Prayman gave the presentation; no public comment. The item was added to the agenda that day.

Sources

Log

2026-04-16 - City Council

Resolution 2026-166 adopted 7-0.