GTL Wastewater and Odor Control

At a glance

  • What: Performance of the GTL wastewater plant and deep-well system in wet weather, and odor control around the plant.
  • Where it stands: no discharges since the last report; the redundant 60-inch force main reaches all five injection wells; four boundary hydrogen sulfide monitors show no hits.
  • Next: final force main connection at the plant in December, needing a two-day bypass.

Sources

Log

2026-11-02 - Infrastructure Advisory Board

  • Flows reached the low 80s MGD without discharges.
  • A floating odorizer was trialed at scum stations and will continue; the pre-treatment building odor project is not yet operational.