Embarcadero West Rail Safety Contract
At a glance
- What: A construction contract for Embarcadero West Rail Safety Phase 1 with O.C. Jones & Sons, $15,240,586.98 plus 25% for change orders (file 27-0204).
- Where it stands: Scheduled on November 5 for the November 17 Special Public Works and Transportation Committee.
Sources
- Rules & Legislation Committee agenda and draft minutes (PDFs), November 5, 2026: https://oakland.legistar.com/View.ashx?M=A&ID=1456404&GUID=2764B050-48FD-427C-A4A3-0CC88793A567
Log
2026-11-05 Rules & Legislation Committee
Scheduled for the November 17 Public Works and Transportation Committee, vote 4 to 0.
2026-11-17 Public Works and Transportation Committee (scheduled)
Contract expected before the committee.