Five-Year Street Rehabilitation Plan
At a glance
- What: The City Manager's Five-Year Street Rehabilitation Plan and Measure FF five-year capital plan for fiscal years 2027 to 2031.
- Where it stands: Adopted July 7, 2026 as Resolution No. 72,377-N.S., all ayes, with added clauses on unfunded safety projects.
- Next: The safety projects named below go back to the SAFE STREETS Citizen Oversight Committee and Council for review and approval.
Detail
- Item 10, public works contact Wahid Amiri. 2 speakers; dozens of written communications (the largest group of letters at the meeting), including from Walk Bike Berkeley.
- Motion (Humbert/Tregub) to adopt the resolution with added clauses: because Council on June 23, 2026 identified the Vision Zero Phased Implementation Plan, Traffic Signal Master Plan, Transportation Fiber Optic Network, Traffic Signal Modernization Project and Transportation Nexus Study as unfunded needs, staff is directed to note them as preliminary Measure FF Safety Projects subject to later review and approval by the SAFE STREETS Citizen Oversight Committee and Council. Vote: all ayes.
Sources
- City Council regular meeting minutes, July 7, 2026: https://berkeleyca.gov/sites/default/files/2026-07/2026-07-28%20Item%2002%20Minutes%20for%20Approval.pdf
Log
2026-07-07 - City Council (regular)
Plan adopted with added clauses, all ayes.