At a glance

  • What: Intergovernmental agreement with the Town of Gilbert and Maricopa County to improve Power Road from State Route 202 (Santan Freeway) to the East Maricopa Floodway (District 6).
  • Where it stands: Approved on the September 28, 2026 consent agenda as Resolution No. 12576; the consent agenda passed 7-0 on a motion by Vice Mayor Somers, seconded by Councilmember Heredia, with no separate discussion.
  • Next: Construction is not expected before Fiscal Year 2032, because the county's first construction payment will not be available before July 1, 2031.

Costs

  • Estimated project cost $61,315,900.
  • Mesa $22,386,364 (36.51 percent), Gilbert $21,190,441 (34.56 percent), Maricopa County $17,739,095 (28.93 percent).

Sources

Log

2026-09-28 - City Council

Resolution No. 12576 approved with the consent agenda, 7-0.