One Chandler Downtown Mixed-use Development
At a glance
- What: Amended and restated development agreement for One Chandler, a $130 million mixed-use downtown project (291 units multifamily, 13,000 SF office, 16,000 SF ground-floor commercial, 612 parking spaces) at northeast corner of Buffalo Street and Arizona Avenue.
- Where it stands: Resolution 6034 approved 7-0 on September 17, 2026; project reassigned to Shelter Asset Management (SAM), LLC from Jackson Dearborn Partners with extended timelines.
- Next: Construction phased through September 2030; minimum improvements completion May 2028 (Tower 1 September 2029, Tower 2 September 2030).
- Watch: Large downtown development; economic benefit cited as approximately 200 full-time jobs, ~$4 million permitting fees, new retail and office opportunities.
Project overview
Developer and ownership:
- Originally approved October 27, 2022 with Jackson Dearborn Partners, LLC.
- Extended December 6, 2024 (one-year extension, commencement of construction extended to March 31, 2026, overall term to March 31, 2030).
- Reassigned to Shelter Asset Management (SAM), LLC (subsidiary of Drewlo Holdings, 69-year-old company with history of long-term tenant retention; average tenancy 9 years, higher than regional average).
- CEO Stu Hansen, President of SAM, attended all weekly planning meetings since partnership began.
Site and zoning:
- Northeast corner of Buffalo Street and Arizona Avenue, downtown Chandler.
- Planned Area Development (PAD) zoning.
- One Chandler rezoned with PAD.
Project scope:
- 291 units multifamily.
- 13,000 SF office.
- 16,000 SF ground-floor commercial.
- 612 self-contained parking spaces.
- Enhanced features: rooftop pool, gathering space, fitness center overlooking Arizona Avenue, monument signage, cantilever patios.
Negotiated deal points:
- Reassignment of development agreement to Shelter Asset Management (SAM), LLC.
- Extended/updated construction deadlines.
- Design modifications consistent with approved Administrative Design Review (ADR) application.
- "Right of first refusal" requirement: if project not fully completed (both towers), developer must give City right of first refusal if wanting to sell any of the property.
Construction timelines:
- 20 business days after closing: initiation of utility relocation work.
- 9 months: 100% Civil Plans for off-site and on-site improvements completion.
- May 2028: completion of minimum improvements.
- September 2029: completion of Tower 1.
- September 2030: completion of Tower 2.
Economic impact
- $130 million total investment.
- Approximately 200 full-time staff to be employed downtown.
- Permitting fees alone approximately $4 million into city revenue.
- Expected to create new retail and office jobs.
- Large economic benefit to Chandler.
Council discussion
- Kim Moyers, Cultural Development Director, presented on developer's commitment and partnership uniqueness.
- Councilmember Ellis: commended staff and company representatives for commitment and work on project; expressed enthusiasm for continued partnership; praised Shelter Asset Management's vision and values.
- Councilmember Orlando: recognized large investment in downtown Chandler; thanked company for investment and hoped for additional future work.
- Councilmember Poston: praised the developer's business model focused on long-term tenant retention.
Vote
- Resolution No. 6034 adopted.
- Motion by Mayor Hartke, seconded by Councilmember Ellis.
- Passed 7-0.
Sources
- City Council Regular Meeting minutes, September 17, 2026: https://public.destinyhosted.com/chanddocs/2026/CC/20260917_2444/2440_City_Council_Regular_Meeting_20260917.pdf
Log
2026-09-17 - City Council
Resolution 6034 approving amended and restated development agreement passed 7-0.