Arena Construction Status

At a glance

  • What: construction of the new downtown arena (Regions Arena), budgeted at $300 million including a $15 million owner's contingency.
  • Where it stands: About 75% complete as of November 3. First event targeted for March 25, 2027, with punch-list work through April. The construction manager projects about $281.6 million against roughly $285 million available after the lost wire-transfer funds, so the project is expected to finish slightly under budget.
  • Next: metal screenwork starts in December, murals and ice-floor work continue; further Finance Committee updates.

Details

  • The $15 million contract contingency will be fully used; about $11.8 million in the furniture and equipment budget will not be spent because items such as the scoreboard moved into the construction contract.
  • The reported fraudulent transfer drew on the owner's contingency; see Reported Fraudulent Wire Transfer.

Sources

Log

2026-11-10 - City Council

  • Res. 01-1211 on the agenda: an agreement with the Mobile County Commission for design and construction of the Regions Arena, $7,500,000. Votes unknown until minutes are posted.

2026-11-03 - Finance Committee

  • Construction manager's update and budget discussion; Council members asked about contingencies and amounts owed (contractors are current).