What: construction of the new downtown arena (Regions Arena), budgeted at $300 million including a $15 million owner's contingency.
Where it stands: About 75% complete as of November 3. First event targeted for March 25, 2027, with punch-list work through April. The construction manager projects about $281.6 million against roughly $285 million available after the lost wire-transfer funds, so the project is expected to finish slightly under budget.
Next: metal screenwork starts in December, murals and ice-floor work continue; further Finance Committee updates.
Details
The $15 million contract contingency will be fully used; about $11.8 million in the furniture and equipment budget will not be spent because items such as the scoreboard moved into the construction contract.
Res. 01-1211 on the agenda: an agreement with the Mobile County Commission for design and construction of the Regions Arena, $7,500,000. Votes unknown until minutes are posted.