  • What: Replacement of the lift at the Hogadon area on Casper Mountain.
  • Where it stands: The 2026-10-13 work session covered a contract of about $3.3 million, $1.41 million in private pledges, a State Land and Investment Board zero-interest loan (10/1) and a needed pre-spending authorization. A contract award was expected per that session, but the 2026-11-03 agenda text did not confirm it.
  • Next: Contract award and pre-spending authorization.

Details

  • No further detail in the records read.

Sources

Log

2026-10-13 - City Council Work Session

  • Lift replacement: about $3.3M contract, $1.41M private pledges, SLIB zero-interest loan, pre-spending authorization needed.

2026-11-03 - City Council

  • No lift contract item appeared in the captioned proceedings.