Pennsylvania Avenue Demolitions and Green Space

At a glance

  • What: demolition of three Pennsylvania Avenue properties and the related green space and pedestrian bridge project.
  • Where it stands: Demolition contract awarded; a memorandum of agreement with the State Historic Preservation Office is being finalized. The pedestrian bridge was delivered and the green space design is substantially complete.
  • Next: Demolition tentatively complete in early December; green space to be bid, with construction expected in spring.

Details

  • The city has right of entry by eminent domain on the properties to come down; one property under contract with the agency is being pursued separately.

Sources

Log

2026-10-22 - Land Reuse and Preservation Agency Regular Meeting

  • Staff update: bridge delivered, design substantially complete, demolition contract awarded with tentative completion in early December.