H Barn Community Building

At a glance

  • What: a community gathering building replacing the old H Barn at Fort Steilacoom Park, meant for events, senior and youth programs, workshops and farmers-market style uses.
  • Where it stands: design is moving from 30 to 60 percent; funding is a mix of City money, a fundraising partner, state money and pending grants.
  • Next: a Council update in December with the 60 percent design; grant decisions expected by the end of 2026; permits targeted before occupancy code changes in May 2027; bidding fall 2027.

Details

  • Roughly 12 million dollars: 1.8 million for design and 10.2 million construction target. A fundraising partner has committed 3.5 million toward a 4 million goal; the City set aside 2 million (1.5 million approved for 2027 to 2029); the state authorized 200,000 dollars for the plaza silos; a state grant ranking is expected in October, with a federal request and a tribal grant request also pending.
  • The City will own the building under a land lease and operating agreement with the partner, which stays advisory on operations and defaults everything back to the City if it exits.
  • Design: open-air pavilion wing, event space of about 160 seated, classroom, plaza, kitchen and storage; parking to be validated at 60 percent.
  • Council also discussed the H Barn in 2026-10-19 - City Council and 2026-11-09 - City Council Study Session.
  • Based on the Whisper transcript of the board meeting; minutes were not read.

Sources

  • Meeting recording of the Parks and Recreation Advisory Board (see the meeting page).

Log

2026-09-22 - Parks and Recreation Advisory Board

  • Staff update to the board: funding picture, design status and schedule; board members supported the project and public commenters asked who will own and schedule the building.