Main Plaza Renovation Contract
At a glance
- What: A construction contract of about $11 million to renovate Main Plaza in District 1, in front of San Fernando Cathedral.
- Where it stands: Pre-solicitation briefing September 2, 2026; solicitation release planned September 22, proposals due November 6.
- Next: Council consideration planned March 2027, funded by certificates of obligation and the Main Plaza Conservancy.
Discussion
- Shannon presented. Meza Gonzalez recommended close coordination with the Archdiocese; Viagran wanted all stories told, substantial community engagement and a strong construction response. Briefing only.
Sources
- Audit Committee 2026-09-02 minutes: https://webapp9.sanantonio.gov/FileNetArchive/{CB1AE589-9F02-4BCF-908C-BDC1F4C1F184}/{CB1AE589-9F02-4BCF-908C-BDC1F4C1F184}.pdf
Log
2026-09-02 - Audit Committee
Pre-solicitation briefing; no action.