- What: Budget amendment and construction contract for the Erwin Park Improvements Project (PK9143), alongside Jim Ledbetter Park (PK2506) and Wattley Park (PK1831) funding.
- Where it stands: On consent June 16, 2026 (unanimous): budget amendment, A&C Construction, Inc. of Irving construction contract, and a Terracon Consultants materials testing contract of $120,805 (up to $140,000 with supplements).
- Next: Construction.
- Data note: Later council meetings (August through October 2026) are known only from agendas or not yet read, so the status below may be out of date.
Bids
- The bid tabulation attached to the minutes (solicitation 26-62CSP) lists six base bids: Millis Development and Construction - Dallas $8,952,160.80; Tegrity Contractors $9,677,777.00; C. Green Scaping $10,046,153.35; A&C Construction $10,088,000.00; RoeschCo Construction $10,230,074.22; CGC General Contractors $10,763,011.10.
- The contract was awarded to A&C Construction, not the lowest bidder. The minutes do not state the contract amount or why; the staff report would explain.
- Related: June 16 ordinance 2026-06-071 amended the FY 2025-2026 budget and CIP for the three park projects.
Sources
- City Council regular meeting minutes, June 16, 2026: https://mckinney.legistar.com/View.ashx?M=M&ID=1421901&GUID=316011AB-FF9F-45F0-BFAC-25D8FAC1FFC2
Log
2026-06-16 - City Council
Budget amendment, A&C Construction contract and Terracon testing contract approved on consent.