At a glance

  • What: Council voted to move forward to bid or renew street maintenance and pavement preservation work using no more than $1 million in certificates of obligation.
  • Where it stands: Approved October 5, 2026, 9-0.

Detail

  • Item 26-C-171, requested by King: continue the preventative street maintenance program begun in the previous fiscal year, identifying funding such as eligible prior certificates of obligation. King moved, Gutierrez seconded; 9-0.
  • Related contracts on the same consent agenda: Springfield Avenues Extension Phase 1 awarded to Soliz Paving, Inc. for up to $3,911,966.60 (220 working days, low of four bids); Shiloh McPherson turn lane project closed out.

Who did what

  • King: Requested and moved.
  • Gutierrez: Seconded.

Sources

Log

2026-10-05 - City Council