  • What: Grant application for Transportation Alternatives (TA) funding to construct shared use path connections and detention pond improvements on South Veterans Parkway.
  • Where it stands: City authorized to apply for federal grant; Resolution No. 112-26 passed 8-0 on October 14, 2026.
  • Project scope: Connect two existing Veterans Parkway underpasses between Cliff Avenue and Sycamore Avenue; construct path around detention pond.
  • City match: 18.05 percent of project cost.
  • Next: Grant application submitted; pending federal funding decisions.

Project details

The City will construct shared use paths connecting to the two existing Veterans Parkway underpasses between Cliff Avenue and Sycamore Avenue, and will construct a path around a detention pond. The City commits to a local match of not less than 18.05 percent of the Project cost and acknowledges responsibility to secure right-of-way or easements.

Vote

Resolution No. 112-26: Passed 8-0 (Basye, Merkouris, Okuwe, Oppenheimer, Pankonin, Sigette, Spellerberg, Thomason voting yes).

Sources

Log

2026-10-14 - City Council

Resolution No. 112-26 passed 8-0, authorizing grant application to South Dakota Department of Transportation for shared use path construction.