Sea Mist PUD Deadline
At a glance
- What: The Sea Mist PUD (Ordinance 2006-25, adopted March 28, 2006) set nine phases on a 20-year minimum construction schedule. The final deadline for Phases 8 and 9 was March 28, 2026, and none of the public improvements have been completed.
- Where it stands: At the September 8, 2026 workshop Mr. Rowe said no construction has started, any schedule extension needs Council approval under Section 14.2, and Planning and Zoning has received no documentation of vested rights under S.C. Code 6-29-1520. The property's MU-H zoning is generally consistent with the surrounding area, so it would be appropriate if the PUD no longer applies.
- Next: No Council action is recorded.
Sources
- City Council workshop and meeting minutes, September 8, 2026: https://cms6.revize.com/revize/myrtlebeachsc/02.%209-8-2026%20Meeting%20Minutes%20.pdf
Log
2026-09-08 - Workshop
Status update presented; no action.