Long Savanna Parkway and Neighborhood 10A Plans

At a glance

  • What: Technical Review Committee reviews of the Long Savanna Parkway (45 acres, 5 lots, West Ashley, priority) and Long Savanna Neighborhood 10A Phase 2 (88 single-family lots at 670 Barons Dr) preliminary plats and road construction plans.
  • Where it stands: Both were on the 2026-09-03 agenda. The Parkway was at its sixth review (first reviewed June 2025); Neighborhood 10A Phase 2 was at its second review. No results have been read.

Sources

Log

2026-09-03 - Technical Review Committee

  • Agenda items 6 to 9: preliminary plat and road construction plans for both projects.

2026-11-05 - Technical Review Committee

  • Agenda items 11 and 12 (11:30, 11:45): Neighborhood 10A Phase 2 preliminary plat and road construction plans (88 lots, 670 Barons Dr), third review. Outcomes not read.