Crescent Park Improvements

At a glance

  • What: a set of purchases, easements and contracts for Crescent Park.
  • Where it stands: The council approved a tent purchase and a Narragansett Electric easement on 2026-09-01, then a slope stabilization contract and an engineering contract for Phase II on 2026-10-06.
  • Next: Phase II work under the engineering contract; no date stated.

Details

  • 2026-09-01: resolutions approved for a Crescent Park tent purchase and a Narragansett Electric easement.
  • 2026-10-06: contract with Lucianos Excavation for slope stabilization, and a contract with FR Engineering not to exceed $200,000 for Phase II of the stabilization, both approved.
  • Crescent Park is also listed among the ARPA projects finishing this year; see ARPA and Capital Projects Progress.

Sources

Log

2026-09-01 - City Council

  • Tent purchase and Narragansett Electric easement approved.

2026-10-06 - City Council

  • Video: Lucianos was the low bidder of six; the state coastal regulator is requiring a stone revetment rather than a vertical seawall.
  • Slope stabilization and Phase II engineering contracts approved.