Data Center Zoning

At a glance

  • What: Ordinance 4236, a Zoning Ordinance text amendment (Sections 2.07 and 5.28) adding a definition of "data center" and allowing data centers as a permitted use in the MH zoning district. Applicant: City of Bellevue.
  • Where it stands: Heard by the Planning Commission on 2026-10-22, introduced to Council on 2026-11-03 and set for public hearing on 2026-11-17. Votes are not in the agendas.
  • Next: Third reading is expected at a later Council meeting.

Sources

Log

2026-11-03 - City Council

  • Ordinance 4236 introduced (first reading).

2026-11-17 - City Council

  • Ordinance 4236: public hearing (second reading).

2026-10-22 - Planning Commission

  • Public hearing on the data center definition and MH district use (Sections 2.07 and 5.28.02).