What: the seating and net upgrade at Centene Stadium.
Where it stands: Construction work was on the August 18 consent agenda; two seating agreements with SP&E were old business on September 15. Outcomes were not read.
Next: Check the September 15 minutes.
Details
August 18: contract of $100,522.77 to A&R Construction for removing box seating and replacing and repairing concrete.
September 15: revised fixed seating purchase agreement with SP&E ($137,837.81) and a seating installation construction agreement with SP&E ($66,900), presented by Toby Hazelbaker.