Colson-Palmer Storm Line Rehabilitation Award
At a glance
- What: Contract with LGC Global, Inc. for $8,975,351 to rehabilitate the 12-foot Colson-Palmer storm line (Dearborn Job No. 2025-19).
- Where it stands: Approved October 6, 2026 (resolution 10-479-26), 6-0, with Paris absent.
- Next: Mayor to sign a formal contract once the Department of Law approves, provided the bid specifications are met.
Detail
- Motion by Enos, supported by Sareini. All other bids received were rejected; only the LGC Global bid was accepted.
- Financed from the Sewer Fund, Public Works, Sewage Division, Capital Project Support, Undistributed budget.
- Immediate effect. Passed 6-0 (Abraham, Alsawafy, Enos, Hammoud, O'Reilly, Sareini yes; Paris absent).
- The posted agenda summarized this as the $8.98 million LGC Global contract; the minutes give the exact amount.
Sources
- City Council minutes, October 6, 2026
- Agenda: https://dearborn.gov/sites/default/files/2026-10/2026-10-06%20-%20Council%20Meeting%20Agenda_1.pdf
Log
2026-10-06 - City Council
Bids other than LGC Global's rejected; LGC Global bid of $8,975,351 accepted on the motion of Enos, supported by Sareini. 6-0.