Red Gate Park and Arboretum

At a glance

  • What: mandatory referral 2027397 MRF from the Recreation and Parks Department for the first phase of Red Gate Park and Arboretum on the 131-acre former golf course at 14500 Avery Road.
  • Where it stands: concept plan approved by the Planning Commission on 2026-10-14, with one commissioner opposed.
  • Next: design and permitting by spring 2027, bidding and award by summer 2027, construction starting fall 2027.

Details

  • The plan implements the Reimagining Red Gate master plan adopted in October 2022. The first phase includes a nature-based inclusive playground, three picnic pavilions, a restroom building, a community garden, a dog park and accessible paths; later phases add an amphitheater, boardwalk, aqua garden and overlook.
  • Staff found the project consistent with the Comprehensive Plan in location, character and extent, and in compliance with the tree preservation and stormwater requirements.
  • A pedestrian connection from MD 28 along Avery Road and other trail links are not yet funded; staff said they will seek funding through the capital budget and can do design work in-house meanwhile.
  • The project is between concept and 30 percent design; the approval covers the overall concept, with materials and boardwalk details deferred. Public art is being coordinated with the city's art and culture manager.

Sources

Log

2026-10-14 - Planning Commission

  • Concept plan approved, one commissioner opposed.