At a glance
- What: Contracts for grant-funded flood and drainage projects, led by a $1,749,968.28 engineering contract with Arcadis for the Bayou Manchac restoration and Ward Creek realignment.
- Where it stands: Arcadis and a $236,087 FEMA-funded Westridge Drive contract were approved; three appraisal and survey contracts were introduced September 9.
- Next: Public hearing on the introduced contracts on September 23, 2026.
Approved
- August 26 (9-0), Resolution 59606: Arcadis U.S., Inc. for the Bayou Manchac Restoration and Ward Creek Realignment Grant Project (No. 26-DR-US-0024), up to $1,749,968.28, funded through the Louisiana Watershed Initiative and contingent on Grants Review Committee approval. Paul Sawyer spoke in favor. Motion Councilman Dunn, second Councilwoman Coleman.
- September 9 (12-0), Resolution 59644: All South Consulting Engineers for the Westridge Drive subsurface system improvements (No. 26-DR-US-0003), up to $236,087.00, funded through FEMA's Hazard Mitigation Grant Program. Motion Councilman Hurst, second Councilwoman Adams.
Introduced September 9
- The Lakvold Group, LLC: appraisal for the Ward Creek Floodplain Easement Acquisition Grant Project (No. 23-DR-US-0028), up to $12,800.00.
- Cook, Moore, Davenport & Associates: appraisal for the Bayou Duplantier Floodplain Easement Acquisition project (No. 23-DR-US-0027), up to $13,000.00.
- Civil Design and Construction, Inc.: Supplemental Agreement No. 1 for added boundary survey, $2,674.78, total $92,009.34.
All are funded through the Louisiana Watershed Initiative.
Related item
See Monte Sano Bayou Drainage Agreement.
Sources
- Metropolitan Council regular meeting minutes, August 26, 2026: https://www.brla.gov/AgendaCenter/ViewFile/Minutes/_08262026-2428
- Metropolitan Council regular meeting minutes, September 9, 2026: https://www.brla.gov/AgendaCenter/ViewFile/Minutes/_09092026-2435
Log
2026-11-10 - Metropolitan Council Regular Meeting
FEMA hazard mitigation engineering contracts among 26-01509 to 26-01516 introduced; see MovEBR Program Contracts for amounts.
2026-09-09 - Metropolitan Council
Westridge Drive contract approved; three floodplain appraisal and survey items introduced.
2026-08-26 - Metropolitan Council
Arcadis contract approved 9-0 with Paul Sawyer speaking in favor.