Cartanza Substation Foundation Change Order
At a glance
- What: Council approved Change Order No. 1 to SEL Engineering Services for reconstruction of deteriorated transformer foundations at Cartanza Substation, increasing the contract from $155,629 to $227,379.
- Where it stands: Approved through acceptance of the Council Committee of the Whole report by consent agenda on September 28, 2026; the committee vote was unanimous on September 15, 2026. (as of the minutes read; later meetings may have updated this)
Built from the official minutes; check the linked source for the authoritative record.
Sources
- 2026-09-15 - Council Committee of the Whole (minutes): https://www.cityofdover.gov/meetingfiles/101495/minutes/fcb541538da547498c3d9ad9fe55d67a.pdf
- 2026-09-28 - Regular City Council (minutes): https://www.cityofdover.gov/meetingfiles/101611/minutes/15335276c9ea40da9d7d5bafaaf39a0e.pdf
Log
2026-09-28 - Regular City Council
Council accepted the Committee of the Whole report by consent agenda, including the Cartanza change order.
2026-09-15 - Council Committee of the Whole
Utility Committee recommended approval of Change Order No. 1 for $71,750, funded within the EE2616 project budget, by motion of Mr. Neil, seconded by Dr. Pillsbury, carried by unanimous roll call with Ms. Arndt and Mr. Iriowen absent.