Westhill High School and New Lower School Projects

At a glance

  • What: school construction items at Westhill High School and 83 Lockwood Ave: a parking license with St. Leo's, demolition of the structures at 83 Lockwood Ave and the New Lower School project (state project 135-0284N).
  • Where it stands: Approved by the Planning Board on 9/22.
  • Next: Construction updates via the Board of Education liaison.

Details

  • The St. Leo's license covers 80 parking spaces for Westhill construction.
  • On 10/5 the Board of Education liaison gave the Board of Representatives a school construction update; the content was not read.
  • The sources read are agendas and, where posted, minutes and action reports; discussion detail is limited to what they record.

Sources

Log

2026-10-05 - Board of Representatives

  • Board of Education liaison gave a school construction update.

2026-09-22 - Planning Board

  • Approved the St. Leo's parking license, demolition at 83 Lockwood Ave and the New Lower School project.

2026-10-27 - Board of Education

2026-10-19 - Board of Representatives Transportation Committee

  • Committee approved 8-0-0 a parking lot lease with a Roxbury Road church for student parking during the Westhill construction; no rent, with city snow removal (up to $10,000 a year) and paving of part of the lot after the project.